Invoiced · 100% complete
Invoiced $27,621
09 Jun 2026 → 17 Jun 2026 · order PO 4484931 · from EST-26-0256 Rev A
Budget against actualOn track
Job value
$27,621
ex GST
Budget cost
$19,943
margin 28%
Actual to date
$20,399
85.5 of 86 hrs
Forecast margin
$7,223
26.1% · $456 over budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Bibra Lake Business Park
- Site
- Units 1–14, Bibra Lake
- Region
- Bibra Lake
- Access
- Tenant notice 24 h
- Site contact
- Rachel Moreau 08 9418 6100
- Lead tech
- Josh Mitchell
- MYOB job
- J-26-0184 in MYOB
Materials — from the estimate (17)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| RG-N2-G | Dry nitrogen — G size cylinder | 0.5 | cyl | BOC Gas & Gear | $49 | $0 | Received | PO-26-0814 | |
| DU-GALV06 | Galvanised sheet 0.6 mm 2400 × 1200 | 6 | sheet | BlueScope Distribution | $276 | $0 | Received | PO-26-0815 | |
| DAI-FDYAN140 | Daikin 14.0 kW ducted split inverter, 1-ph (FDYAN140) | 2 | ea | Daikin Australia | $10,971 | $0 | Received | PO-26-0811 | |
| CT-BRC1H | Daikin wired controller (BRC1H) | 2 | ea | Daikin Australia | $427 | $0 | Received | PO-26-0811 | |
| DU-FLX250 | Insulated flexible duct 250 mm × 6 m | 12 | length | Holyoake | $864 | $0 | Received | PO-26-0813 | |
| DU-DIF450 | Ceiling diffuser 4-way 450 sq. with plenum | 12 | ea | Holyoake | $552 | $0 | Received | PO-26-0813 | |
| DU-RAG600 | Return air grille 600 × 600 with filter | 2 | ea | Holyoake | $148 | $0 | Received | PO-26-0813 | |
| DU-SPG250 | Spigot collar 250 mm with damper | 12 | ea | Holyoake | $216 | $0 | Received | PO-26-0813 | |
| DU-VCD300 | Volume control damper 300 × 300 | 1 | ea | Holyoake | $48 | $0 | Received | PO-26-0813 | |
| CU-PR3858 | Pre-insulated pair coil 3/8" + 5/8" × 20 m | 2 | coil | Reece HVAC-R | $684 | $0 | Received | PO-26-0810 | |
| INS-DUCTR1 | Duct insulation blanket R1.0 × 15 m roll | 2 | roll | Reece HVAC-R | $224 | $0 | Received | PO-26-0810 | |
| DU-MASTIC | Duct mastic & foil tape kit | 6 | kit | Reece HVAC-R | $132 | $0 | Received | PO-26-0810 | |
| MS-PADS | Anti-vibration pads (set of 4) | 2 | set | Reece HVAC-R | $44 | $0 | Received | PO-26-0810 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 2 | set | Reece HVAC-R | $56 | $0 | Received | PO-26-0810 | |
| MS-SUND | Fixings & sundries allowance | 3 | lot | Reece HVAC-R | $105 | $0 | Received | PO-26-0810 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 2 | ea | Rexel Electrical | $72 | $0 | Received | PO-26-0812 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 50 | m | Rexel Electrical | $115 | $0 | Received | PO-26-0812 | |
Purchase orders (6)All POs →
Invoices$27,621 of $27,621
INV-4291 Final18 Jun 2026 · MYOB #00004291
Paid$27,621 Timesheets — 85.5 hrs · $5,074 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 11 Jun 2026 | Kyle Fraser | 2.5 | $170 | — | |
| 11 Jun 2026 | Sam Nguyen | 4 | $304 | — | |
| 11 Jun 2026 | Ben Harris | 8 | $256 | — | |
| 11 Jun 2026 | Josh Mitchell | 8 | $576 | — | |
| 10 Jun 2026 | Kyle Fraser | 6 | $408 | — | |
| 10 Jun 2026 | Sam Nguyen | 5 | $380 | — | |
| 10 Jun 2026 | Ben Harris | 10 | $320 | — | |
| 10 Jun 2026 | Josh Mitchell | 8 | $576 | — | |
| 09 Jun 2026 | Kyle Fraser | 8 | $544 | Mobilise, set out | |
| 09 Jun 2026 | Sam Nguyen | 7 | $532 | Mobilise, set out | |
| 09 Jun 2026 | Ben Harris | 9 | $288 | Mobilise, set out | |
| 09 Jun 2026 | Josh Mitchell | 10 | $720 | Mobilise, set out | |