NotificationsMark all read
MYOB sync completeInvoices, purchase orders and jobs up to date with MYOB AccountRight
08 Oct 2026 · 09:14
Materials deliveredPO-26-0913 BOC Gas & Gear received for J-26-0235
08 Oct 2026 · 08:30
Invoice overdueINV-4311 Bibra Lake Business Park — due 2026-09-04
08 Oct 2026 · 08:05
Price change on open estimates2 open estimates priced before the Sep refrigerant increase — margin down
08 Oct 2026 · 07:52
Estimate acceptedEST-26-0297 Kwinana fab shop — office ducted 14 kW
07 Oct 2026 · 15:42
Activity log
Michelle · Estimate EST-26-0303 created — Consult rooms 4–7 — ducted 14 kW + zoning07 Oct 2026 · 10:26
Matthew Jacka · Estimate EST-26-0302 created — Cockburn ARC — rooftop packaged unit replacement (RTU-3)06 Oct 2026 · 10:34
Michelle · Estimate EST-26-0301 sent to Michael Tan04 Oct 2026 · 14:22
Michelle · Purchase order PO-26-0919 sent to Daikin Australia03 Oct 2026 · 11:47
Michelle · Purchase order PO-26-0918 sent to Reece HVAC-R03 Oct 2026 · 11:41
Michelle · Purchase order PO-26-0920 sent to Rexel Electrical03 Oct 2026 · 11:38
Michelle · Purchase order PO-26-0917 sent to Rexel Electrical02 Oct 2026 · 11:59
Michelle · Purchase order PO-26-0916 sent to Mitsubishi Electric02 Oct 2026 · 11:41
Michelle · Purchase order PO-26-0915 sent to Actrol02 Oct 2026 · 11:35
Michelle · Purchase order PO-26-0914 sent to Reece HVAC-R02 Oct 2026 · 11:28
Michelle · Estimate EST-26-0301 created — Switchroom cooling upgrade — SR1 to SR402 Oct 2026 · 10:35
Matthew Jacka · Estimate EST-26-0300 sent to Brendan Clancy01 Oct 2026 · 14:55
Michelle · Estimate EST-26-0299 sent to Sophie Lindqvist29 Sep 2026 · 14:40
Michelle · Purchase order PO-26-0911 sent to Rexel Electrical29 Sep 2026 · 11:57
Michelle · Purchase order PO-26-0910 sent to Daikin Australia29 Sep 2026 · 11:57
Michelle · Purchase order PO-26-0909 sent to Reece HVAC-R29 Sep 2026 · 11:56
Michelle · Purchase order PO-26-0912 sent to Holyoake29 Sep 2026 · 11:50
Michelle · Purchase order PO-26-0913 sent to BOC Gas & Gear29 Sep 2026 · 11:29
Matthew Jacka · Estimate EST-26-0300 created — Roy Hill village — donga AC replacement, Block C (24 rooms)29 Sep 2026 · 10:10
Michelle · Estimate EST-26-0299 created — Terminal offices — 2 × ducted 20 kW replacement26 Sep 2026 · 10:33