Invoiced · 100% complete
Invoiced $24,445
11 Feb 2026 → 16 Feb 2026 · order PO 4700867 · from EST-26-0226 Rev A
Budget against actualOn track
Job value
$24,445
ex GST
Budget cost
$17,346
margin 29%
Actual to date
$16,785
90.5 of 80 hrs
Forecast margin
$7,660
31.3% · $561 under budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Gold Fields Australia
- Site
- St Ives gold mine — admin & crib rooms
- Region
- Goldfields · Kambalda
- Access
- DIDO · St Ives induction
- Site contact
- Tom Ferreira 08 9211 9200
- Lead tech
- Liam O'Brien
- MYOB job
- J-26-0135 in MYOB
Materials — from the estimate (10)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| CT-DUTY | Duty / standby changeover controller with alarm relay | 2 | ea | Actrol | $1,280 | $0 | Received | PO-26-0704 | |
| MEA-MSZAP71 | Mitsubishi Electric 7.1 kW wall split (MSZ-AP71VG) | 4 | ea | Mitsubishi Electric | $8,160 | $0 | Received | PO-26-0705 | |
| CU-PR1438 | Pre-insulated pair coil 1/4" + 3/8" × 20 m | 4 | coil | Reece HVAC-R | $911 | $0 | Received | PO-26-0703 | |
| MS-BRK750 | Wall bracket 750 mm heavy duty, galv | 4 | pr | Reece HVAC-R | $192 | $0 | Received | PO-26-0703 | |
| MS-PADS | Anti-vibration pads (set of 4) | 4 | set | Reece HVAC-R | $88 | $0 | Received | PO-26-0703 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 4 | set | Reece HVAC-R | $112 | $0 | Received | PO-26-0703 | |
| MS-SUND | Fixings & sundries allowance | 4 | lot | Reece HVAC-R | $140 | $0 | Received | PO-26-0703 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 4 | ea | Rexel Electrical | $144 | $0 | Received | PO-26-0706 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 60 | m | Rexel Electrical | $137 | $0 | Received | PO-26-0706 | |
| EL-CON25 | Conduit 25 mm × 4 m + saddles | 12 | length | Rexel Electrical | $90 | $0 | Received | PO-26-0706 | |
Purchase orders (4)All POs →
Invoices$24,445 of $24,445
INV-4241 Final17 Feb 2026 · MYOB #00004241
Paid$24,445 Timesheets — 90.5 hrs · $5,531 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 16 Feb 2026 | Tayla Brooks | 7.5 | $285 | — | |
| 16 Feb 2026 | Liam O'Brien | 9 | $666 | — | |
| 13 Feb 2026 | Sam Nguyen | 4 | $304 | — | |
| 13 Feb 2026 | Tayla Brooks | 9 | $342 | — | |
| 13 Feb 2026 | Liam O'Brien | 9 | $666 | — | |
| 12 Feb 2026 | Sam Nguyen | 8 | $608 | — | |
| 12 Feb 2026 | Tayla Brooks | 9 | $342 | — | |
| 12 Feb 2026 | Liam O'Brien | 11 | $814 | — | |
| 11 Feb 2026 | Sam Nguyen | 8 | $608 | Mobilise, set out | |
| 11 Feb 2026 | Tayla Brooks | 8 | $304 | Mobilise, set out | |
| 11 Feb 2026 | Liam O'Brien | 8 | $592 | Mobilise, set out | |