WA HVAC

EST-26-0272 Rev A

Jandakot Airport Holdings · Jandakot Airport — workshop exhaust & cooling
MYOB · synced 09:14 Demo 08 Oct 2026
Accepted
Accepted 17 Jul 2026 — job J-26-0210 raised
Jandakot Airport — terminal & offices · Jandakot · prepared by Matthew Jacka
Cost
$28,713
150 labour hrs · $9,084
Price ex GST
$41,215
20 lines · 2 groups
Margin
$12,502
30.3% of price
Total inc GST
$45,336
GST $4,121.47
Bill of materials & labour Accepted
ItemQtyUnitUnit costMarkupUnit sellLine
Exhaust fan & ducting — kitchen / ablutions × 6$16,012
FT-TD250
Fantech inline mixed-flow fan 250 mm (TD-1300/250)
6 ea $680.00 30% $884.00 $5,304.00
DU-FLX250
Insulated flexible duct 250 mm × 6 m
12 length $72.00 35% $97.20 $1,166.40
DU-SPG250
Spigot collar 250 mm with damper
12 ea $18.00 35% $24.30 $291.60
EL-ISO20
Isolator 20 A 2-pole IP66
6 ea $36.00 35% $48.60 $291.60
EL-TPS25
2.5 mm² TPS cable × 100 m
0.6 roll $160.00 30% $208.00 $124.80
MS-SUND
Fixings & sundries allowance
6 lot $35.00 35% $47.25 $283.50
LAB-MECH
Refrigeration mechanic
36 hr $72.00 73.6% $125.00 $4,500.00
LAB-ELEC
Electrician
18 hr $76.00 64.5% $125.00 $2,250.00
LAB-APP
Apprentice
24 hr $38.00 97.4% $75.00 $1,800.00
Wall split 7.1 kW — back-to-back install × 6$25,203
DAI-FTXM71
Daikin 7.1 kW wall split inverter (FTXM71)
6 ea $1,890.00 25% $2,362.50 $14,175.00
CU-PR1438
Pre-insulated pair coil 1/4" + 3/8" × 20 m
6 coil $238.00 35% $321.30 $1,927.80
MS-BRK750
Wall bracket 750 mm heavy duty, galv
6 pr $48.00 35% $64.80 $388.80
MS-PADS
Anti-vibration pads (set of 4)
6 set $22.00 35% $29.70 $178.20
EL-ISO20
Isolator 20 A 2-pole IP66
6 ea $36.00 35% $48.60 $291.60
EL-IC415
Interconnect cable 4C 1.5 mm²
72 m $2.29 40% $3.21 $231.12
MS-DRAIN
Condensate drain 20 mm PVC + fittings
6 set $28.00 35% $37.80 $226.80
MS-SUND
Fixings & sundries allowance
6 lot $35.00 35% $47.25 $283.50
LAB-MECH
Refrigeration mechanic
30 hr $72.00 73.6% $125.00 $3,750.00
LAB-APP
Apprentice
30 hr $38.00 97.4% $75.00 $2,250.00
LAB-ELEC
Electrician
12 hr $76.00 64.5% $125.00 $1,500.00
Scope & exclusions
Supply, install and commission as per the line items. Includes electrical isolation, refrigerant charge, testing and a commissioning report.
Exclusions: Builder's works, penetrations through fire-rated elements, after-hours work unless noted, structural certification. Flights and camp accommodation supplied by client on remote sites.
Client & site
Client
Jandakot Airport Holdings
Contact
Sophie Lindqvist · 08 9417 2000
Site
Jandakot Airport — terminal & offices
Access
Airside pass for roof access
Terms
30 days EOM
Priced on
08 Jul 2026