Invoiced · 100% complete
Invoiced $21,380
31 Jul 2026 → 04 Aug 2026 · order PO 4789545 · from EST-26-0271 Rev A
Budget against actualOn track
Job value
$21,380
ex GST
Budget cost
$15,287
margin 28%
Actual to date
$14,740
58.5 of 64 hrs
Forecast margin
$6,640
31.1% · $547 under budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Bibra Lake Business Park
- Site
- Units 1–14, Bibra Lake
- Region
- Bibra Lake
- Access
- Tenant notice 24 h
- Site contact
- Rachel Moreau 08 9418 6100
- Lead tech
- Craig Whitfield
- MYOB job
- J-26-0205 in MYOB
Materials — from the estimate (10)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| CT-DUTY | Duty / standby changeover controller with alarm relay | 2 | ea | Actrol | $1,280 | $0 | Received | PO-26-0857 | |
| MEA-MSZAP71 | Mitsubishi Electric 7.1 kW wall split (MSZ-AP71VG) | 4 | ea | Mitsubishi Electric | $8,160 | $0 | Received | PO-26-0858 | |
| CU-PR1438 | Pre-insulated pair coil 1/4" + 3/8" × 20 m | 4 | coil | Reece HVAC-R | $952 | $0 | Received | PO-26-0856 | |
| MS-BRK750 | Wall bracket 750 mm heavy duty, galv | 4 | pr | Reece HVAC-R | $192 | $0 | Received | PO-26-0856 | |
| MS-PADS | Anti-vibration pads (set of 4) | 4 | set | Reece HVAC-R | $88 | $0 | Received | PO-26-0856 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 4 | set | Reece HVAC-R | $112 | $0 | Received | PO-26-0856 | |
| MS-SUND | Fixings & sundries allowance | 4 | lot | Reece HVAC-R | $140 | $0 | Received | PO-26-0856 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 4 | ea | Rexel Electrical | $144 | $0 | Received | PO-26-0859 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 60 | m | Rexel Electrical | $137 | $0 | Received | PO-26-0859 | |
| EL-CON25 | Conduit 25 mm × 4 m + saddles | 12 | length | Rexel Electrical | $90 | $0 | Received | PO-26-0859 | |
Purchase orders (4)All POs →
Invoices$21,380 of $21,380
INV-4311 Final05 Aug 2026 · MYOB #00004311
Overdue$21,380 Timesheets — 58.5 hrs · $3,445 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 03 Aug 2026 | Craig Whitfield | 7.5 | $525 | — | |
| 03 Aug 2026 | Sam Nguyen | 4 | $304 | — | |
| 03 Aug 2026 | Ben Harris | 9 | $288 | — | |
| 03 Aug 2026 | Craig Whitfield | 10 | $700 | — | |
| 31 Jul 2026 | Sam Nguyen | 8 | $608 | Mobilise, set out | |
| 31 Jul 2026 | Ben Harris | 10 | $320 | Mobilise, set out | |
| 31 Jul 2026 | Craig Whitfield | 10 | $700 | Mobilise, set out | |