WA HVAC Pty Ltd
1/9 Blackly Row, Cockburn Central WA 6164 · 08 9314 7696 · admin@wahvac.com.au
ABN 49 629 340 405 · Refrigerant Trading Authorisation AU42942 · Electrical Contractor EC10155
Quotation
EST-26-0249 Rev A
Date 23 Apr 2026
Valid until 24 May 2026
Prepared by Michelle
Prepared for
Kwinana Bulk Terminal
Attn: Steve Galvin
sgalvin@kbt.com.au
ABN 40 715 228 663
Site
KBT — admin & crib
Kwinana
KBT — donga AC changeover
| Description | Amount ex GST |
|---|---|
Donga / transportable split 2.5 kW — per room × 36 36 × Daikin 2.5 kW wall split — transportable/donga (FTXF25) · 18 × Pre-insulated pair coil 1/4" + 3/8" × 20 m · 36 × Wall bracket 750 mm heavy duty, galv · 36 × Isolator 20 A 2-pole IP66 · 288 × Interconnect cable 4C 1.5 mm² · 36 × Condensate drain 20 mm PVC + fittings · 18 × Fixings & sundries allowance · Installation, testing & commissioning (216 hrs) | $67,805.46 |
| Subtotal (ex GST) | $67,805.46 |
| GST 10% | $6,780.55 |
| Total (inc GST) | $74,586.01 |
This quotation is valid for 30 days. Prices are based on supplier costs on 22 Apr 2026.
Exclusions: Builder's works, penetrations through fire-rated elements, after-hours work unless noted, structural certification. Flights and camp accommodation supplied by client on remote sites.
Payment terms per our account terms. All work carried out by ARCtick-licensed technicians under RTA AU42942 and EC10155.
Heating · Ventilation · Air Conditioning · Refrigeration · Maintenance