Accepted
Accepted 19 Oct 2025 — job J-25-0106 raised
Kwinana — control room & labs · Kwinana · prepared by Matthew Jacka
Cost
$23,948
120 labour hrs · $6,852
Price ex GST
$34,112
16 lines · 1 groups
Margin
$10,164
29.8% of price
Total inc GST
$37,523
GST $3,411.23
Bill of materials & labour Accepted
| Item | Qty | Unit | Unit cost | Markup | Unit sell | Line | |
|---|---|---|---|---|---|---|---|
| Coolroom refrigeration — medium temp × 3 | $34,112 | ||||||
| HC-LET068 Heatcraft condensing unit 1.5 HP medium temp (R448A) | 3 | ea | $3,180.00 | 25% | $3,975.00 | $11,925.00 | |
| KB-EVMT26 Kirby coolroom evaporator, medium temp 2.6 kW | 3 | ea | $1,240.00 | 28% | $1,587.20 | $4,761.60 | |
| CT-XR60 Dixell XR60CX coolroom controller kit | 3 | ea | $310.00 | 30% | $403.00 | $1,209.00 | |
| CU-C38-15 Copper tube 3/8" soft coil × 15 m | 3 | coil | $103.35 | 35% | $139.52 | $418.56 | |
| CU-C58-15 Copper tube 5/8" soft coil × 15 m | 3 | coil | $179.90 | 35% | $242.87 | $728.61 | |
| INS-AF58 Armaflex 5/8" ID × 19 mm × 1.8 m | 24 | length | $10.00 | 35% | $13.50 | $324.00 | |
| CU-FIT-PK Copper fittings pack — elbows, couplers, tees | 3 | pack | $55.50 | 35% | $74.93 | $224.79 | |
| RG-BRZ15 Silver brazing rod 15% — 1 kg | 0.75 | pack | $165.00 | 30% | $214.50 | $160.88 | |
| RG-N2-G Dry nitrogen — G size cylinder | 1.5 | cyl | $98.00 | 30% | $127.40 | $191.10 | |
| RG-R448-10 Refrigerant R448A — 10 kg cylinder | 1.8 | cyl | $571.43 | 35% | $771.43 | $1,388.57 | |
| EL-ISO20 Isolator 20 A 2-pole IP66 | 3 | ea | $36.00 | 35% | $48.60 | $145.80 | |
| EL-IC415 Interconnect cable 4C 1.5 mm² | 60 | m | $2.29 | 40% | $3.21 | $192.60 | |
| MS-SUND Fixings & sundries allowance | 3 | lot | $35.00 | 35% | $47.25 | $141.75 | |
| LAB-MECH Refrigeration mechanic | 54 | hr | $72.00 | 73.6% | $125.00 | $6,750.00 | |
| LAB-APP Apprentice | 54 | hr | $38.00 | 97.4% | $75.00 | $4,050.00 | |
| LAB-ELEC Electrician | 12 | hr | $76.00 | 64.5% | $125.00 | $1,500.00 | |
Scope & exclusions
Supply, install and commission as per the line items. Includes electrical isolation, refrigerant charge, testing and a commissioning report.
Exclusions: Builder's works, penetrations through fire-rated elements, after-hours work unless noted, structural certification. Flights and camp accommodation supplied by client on remote sites.
Client & site
- Client
- CSBP Kwinana
- Contact
- Andrea Novak · 08 9411 8777
- Site
- Kwinana — control room & labs
- Access
- Major hazard facility · permit to work
- Terms
- 30 days EOM
- Priced on
- 12 Oct 2025