Invoiced · 100% complete
Invoiced $30,266
03 Nov 2025 → 12 Nov 2025 · order PO 4553116 · from EST-25-0205 Rev A
Budget against actualOn track
Job value
$30,266
ex GST
Budget cost
$20,981
margin 31%
Actual to date
$19,941
112 of 116 hrs
Forecast margin
$10,325
34.1% · $1,040 under budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Gold Fields Australia
- Site
- St Ives gold mine — admin & crib rooms
- Region
- Goldfields · Kambalda
- Access
- DIDO · St Ives induction
- Site contact
- Tom Ferreira 08 9211 9200
- Lead tech
- Dean Kowalski
- MYOB job
- J-25-0105 in MYOB
Materials — from the estimate (12)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| DAI-FTXM71 | Daikin 7.1 kW wall split inverter (FTXM71) | 4 | ea | Daikin Australia | $7,340 | $0 | Received | PO-25-0623 | |
| FT-TD250 | Fantech inline mixed-flow fan 250 mm (TD-1300/250) | 4 | ea | Fantech | $2,720 | $0 | Received | PO-25-0626 | |
| DU-FLX250 | Insulated flexible duct 250 mm × 6 m | 8 | length | Holyoake | $576 | $0 | Received | PO-25-0625 | |
| DU-SPG250 | Spigot collar 250 mm with damper | 8 | ea | Holyoake | $144 | $0 | Received | PO-25-0625 | |
| CU-PR1438 | Pre-insulated pair coil 1/4" + 3/8" × 20 m | 4 | coil | Reece HVAC-R | $911 | $0 | Received | PO-25-0622 | |
| MS-BRK750 | Wall bracket 750 mm heavy duty, galv | 4 | pr | Reece HVAC-R | $192 | $0 | Received | PO-25-0622 | |
| MS-PADS | Anti-vibration pads (set of 4) | 4 | set | Reece HVAC-R | $88 | $0 | Received | PO-25-0622 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 4 | set | Reece HVAC-R | $112 | $0 | Received | PO-25-0622 | |
| MS-SUND | Fixings & sundries allowance | 8 | lot | Reece HVAC-R | $280 | $0 | Received | PO-25-0622 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 8 | ea | Rexel Electrical | $288 | $0 | Received | PO-25-0624 | |
| EL-TPS25 | 2.5 mm² TPS cable × 100 m | 0.4 | roll | Rexel Electrical | $64 | $0 | Received | PO-25-0624 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 48 | m | Rexel Electrical | $110 | $0 | Received | PO-25-0624 | |
Purchase orders (5)All POs →
Invoices$30,266 of $30,266
INV-4205 Final13 Nov 2025 · MYOB #00004205
Paid$30,266 Timesheets — 112 hrs · $7,116 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 07 Nov 2025 | Tayla Brooks | 7 | $266 | — | |
| 07 Nov 2025 | Dean Kowalski | 9 | $738 | — | |
| 06 Nov 2025 | Sam Nguyen | 7 | $532 | — | |
| 06 Nov 2025 | Tayla Brooks | 9 | $342 | — | |
| 06 Nov 2025 | Dean Kowalski | 11 | $902 | — | |
| 05 Nov 2025 | Sam Nguyen | 4 | $304 | — | |
| 05 Nov 2025 | Tayla Brooks | 11 | $418 | — | |
| 05 Nov 2025 | Dean Kowalski | 9 | $738 | — | |
| 04 Nov 2025 | Sam Nguyen | 7 | $532 | — | |
| 04 Nov 2025 | Tayla Brooks | 8 | $304 | — | |
| 04 Nov 2025 | Dean Kowalski | 8 | $656 | — | |
| 03 Nov 2025 | Sam Nguyen | 4 | $304 | Mobilise, set out | |
| 03 Nov 2025 | Tayla Brooks | 9 | $342 | Mobilise, set out | |
| 03 Nov 2025 | Dean Kowalski | 9 | $738 | Mobilise, set out | |