J-25-0105 · St Ives gold mine — workshop exhaust & cooling

Gold Fields Australia · St Ives gold mine — admin & crib rooms · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $30,266
03 Nov 2025 → 12 Nov 2025 · order PO 4553116 · from EST-25-0205 Rev A
Budget against actualOn track
Job value
$30,266
ex GST
Budget cost
$20,981
margin 31%
Actual to date
$19,941
112 of 116 hrs
Forecast margin
$10,325
34.1% · $1,040 under budget
Materials
$12,825 / $12,825
Labour
$7,116 / $8,156
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Gold Fields Australia
Site
St Ives gold mine — admin & crib rooms
Region
Goldfields · Kambalda
Access
DIDO · St Ives induction
Site contact
Tom Ferreira 08 9211 9200
Lead tech
Dean Kowalski
MYOB job
J-25-0105 in MYOB
Materials — from the estimate (12)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXM71 Daikin 7.1 kW wall split inverter (FTXM71) 4 ea Daikin Australia $7,340 $0 Received PO-25-0623
FT-TD250 Fantech inline mixed-flow fan 250 mm (TD-1300/250) 4 ea Fantech $2,720 $0 Received PO-25-0626
DU-FLX250 Insulated flexible duct 250 mm × 6 m 8 length Holyoake $576 $0 Received PO-25-0625
DU-SPG250 Spigot collar 250 mm with damper 8 ea Holyoake $144 $0 Received PO-25-0625
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 4 coil Reece HVAC-R $911 $0 Received PO-25-0622
MS-BRK750 Wall bracket 750 mm heavy duty, galv 4 pr Reece HVAC-R $192 $0 Received PO-25-0622
MS-PADS Anti-vibration pads (set of 4) 4 set Reece HVAC-R $88 $0 Received PO-25-0622
MS-DRAIN Condensate drain 20 mm PVC + fittings 4 set Reece HVAC-R $112 $0 Received PO-25-0622
MS-SUND Fixings & sundries allowance 8 lot Reece HVAC-R $280 $0 Received PO-25-0622
EL-ISO20 Isolator 20 A 2-pole IP66 8 ea Rexel Electrical $288 $0 Received PO-25-0624
EL-TPS25 2.5 mm² TPS cable × 100 m 0.4 roll Rexel Electrical $64 $0 Received PO-25-0624
EL-IC415 Interconnect cable 4C 1.5 mm² 48 m Rexel Electrical $110 $0 Received PO-25-0624
Timesheets — 112 hrs · $7,116 at cost
DateWhoHoursCostNote
07 Nov 2025 Tayla Brooks 7 $266 —
07 Nov 2025 Dean Kowalski 9 $738 —
06 Nov 2025 Sam Nguyen 7 $532 —
06 Nov 2025 Tayla Brooks 9 $342 —
06 Nov 2025 Dean Kowalski 11 $902 —
05 Nov 2025 Sam Nguyen 4 $304 —
05 Nov 2025 Tayla Brooks 11 $418 —
05 Nov 2025 Dean Kowalski 9 $738 —
04 Nov 2025 Sam Nguyen 7 $532 —
04 Nov 2025 Tayla Brooks 8 $304 —
04 Nov 2025 Dean Kowalski 8 $656 —
03 Nov 2025 Sam Nguyen 4 $304 Mobilise, set out
03 Nov 2025 Tayla Brooks 9 $342 Mobilise, set out
03 Nov 2025 Dean Kowalski 9 $738 Mobilise, set out