Accepted
Accepted 20 Sep 2026 — job J-26-0234 raised
Bluebird — Meekatharra · Murchison · Meekatharra · prepared by Michelle
Cost
$9,744
48 labour hrs · $4,096
Price ex GST
$13,810
15 lines · 2 groups
Margin
$4,067
29.4% of price
Total inc GST
$15,191
GST $1,381.02
Bill of materials & labour Accepted
| Item | Qty | Unit | Unit cost | Markup | Unit sell | Line | |
|---|---|---|---|---|---|---|---|
| Switchroom cooling — 2 × 7.1 kW duty/standby | $10,690 | ||||||
| MEA-MSZAP71 Mitsubishi Electric 7.1 kW wall split (MSZ-AP71VG) | 2 | ea | $2,040.00 | 25% | $2,550.00 | $5,100.00 | |
| CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m | 2 | coil | $238.00 | 35% | $321.30 | $642.60 | |
| MS-BRK750 Wall bracket 750 mm heavy duty, galv | 2 | pr | $48.00 | 35% | $64.80 | $129.60 | |
| MS-PADS Anti-vibration pads (set of 4) | 2 | set | $22.00 | 35% | $29.70 | $59.40 | |
| EL-ISO20 Isolator 20 A 2-pole IP66 | 2 | ea | $36.00 | 35% | $48.60 | $97.20 | |
| EL-IC415 Interconnect cable 4C 1.5 mm² | 30 | m | $2.29 | 40% | $3.21 | $96.30 | |
| EL-CON25 Conduit 25 mm × 4 m + saddles | 6 | length | $7.50 | 40% | $10.50 | $63.00 | |
| CT-DUTY Duty / standby changeover controller with alarm relay | 1 | ea | $640.00 | 30% | $832.00 | $832.00 | |
| MS-DRAIN Condensate drain 20 mm PVC + fittings | 2 | set | $28.00 | 35% | $37.80 | $75.60 | |
| MS-SUND Fixings & sundries allowance | 2 | lot | $35.00 | 35% | $47.25 | $94.50 | |
| LAB-MECH Refrigeration mechanic | 14 | hr | $72.00 | 73.6% | $125.00 | $1,750.00 | |
| LAB-APP Apprentice | 10 | hr | $38.00 | 97.4% | $75.00 | $750.00 | |
| LAB-ELEC Electrician | 8 | hr | $76.00 | 64.5% | $125.00 | $1,000.00 | |
| Regional mobilisation — 2-person crew | $3,120 | ||||||
| TRV-TIME Travel time — regional (per person) | 16 | hr | $60.00 | 50% | $90.00 | $1,440.00 | |
| TRV-KM Service vehicle — regional travel | 1,200 | km | $0.95 | 47.4% | $1.40 | $1,680.00 | |
Scope & exclusions
Supply, install and commission as per the line items. Includes electrical isolation, refrigerant charge, testing and a commissioning report.
Exclusions: Builder's works, penetrations through fire-rated elements, after-hours work unless noted, structural certification. Flights and camp accommodation supplied by client on remote sites.
Client & site
- Client
- Westgold Resources
- Contact
- Lisa Carmody · 08 9462 3400
- Site
- Bluebird — Meekatharra
- Access
- FIFO · site induction
- Terms
- 30 days EOM
- Priced on
- 14 Sep 2026