Materials ordered · 0% complete
Lead: Dean Kowalski · due 19 Oct 2026
12 Oct 2026 → 19 Oct 2026 · order WGX-PO-88201 · from EST-26-0294 Rev A
Budget against actualOn track
Job value
$13,810
ex GST
Budget cost
$9,744
margin 29%
Actual to date
$5,651
0 of 48 hrs
Forecast margin
$4,063
29.4% · $3 over budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Westgold Resources
- Site
- Bluebird — Meekatharra
- Region
- Murchison · Meekatharra
- Access
- FIFO · site induction
- Site contact
- Lisa Carmody 08 9462 3400
- Lead tech
- Dean Kowalski
- MYOB job
- J-26-0234 in MYOB
Materials — from the estimate (10)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| CT-DUTY | Duty / standby changeover controller with alarm relay | 1 | ea | Actrol | $640 | $0 | Ordered | PO-26-0915 | |
| MEA-MSZAP71 | Mitsubishi Electric 7.1 kW wall split (MSZ-AP71VG) | 2 | ea | Mitsubishi Electric | $4,080 | $0 | Ordered | PO-26-0916 | |
| CU-PR1438 | Pre-insulated pair coil 1/4" + 3/8" × 20 m | 2 | coil | Reece HVAC-R | $476 | $0 | Ordered | PO-26-0914 | |
| MS-BRK750 | Wall bracket 750 mm heavy duty, galv | 2 | pr | Reece HVAC-R | $96 | $0 | Ordered | PO-26-0914 | |
| MS-PADS | Anti-vibration pads (set of 4) | 2 | set | Reece HVAC-R | $44 | $0 | Ordered | PO-26-0914 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 2 | set | Reece HVAC-R | $56 | $0 | Ordered | PO-26-0914 | |
| MS-SUND | Fixings & sundries allowance | 2 | lot | Reece HVAC-R | $70 | $0 | Ordered | PO-26-0914 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 2 | ea | Rexel Electrical | $72 | $0 | Ordered | PO-26-0917 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 30 | m | Rexel Electrical | $69 | $0 | Ordered | PO-26-0917 | |
| EL-CON25 | Conduit 25 mm × 4 m + saddles | 6 | length | Rexel Electrical | $45 | $0 | Ordered | PO-26-0917 | |
Purchase orders (4)All POs →
Invoices$0 of $13,810
Not invoiced yet.
Timesheets — 0 hrs · $0 at cost
| Date | Who | Hours | Cost | Note |
|---|
Nothing here yet — use “Log hours” to create the first one.