J-26-0228 · Gap Ridge Village — donga AC replacement, Wing D (28 rooms)

Civeo · Gap Ridge Village · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Materials ordered · 0% complete
Lead: Josh Mitchell · due 26 Oct 2026
14 Oct 2026 → 26 Oct 2026 · order CIV-GRV-3318 · from EST-26-0289 Rev A
Budget against actualOn track
Job value
$59,752
ex GST
Budget cost
$42,191
margin 29%
Actual to date
$28,776
0 of 200 hrs
Forecast margin
$17,537
29.3% · $25 over budget
Materials
$28,776 / $28,751
Labour
$0 / $13,440
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Civeo
Site
Gap Ridge Village
Region
Pilbara · Karratha
Access
Drive-in · village reception
Site contact
Shane Mathers 08 9473 1800
Lead tech
Josh Mitchell
MYOB job
J-26-0228 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXF25 Daikin 2.5 kW wall split — transportable/donga (FTXF25) 28 ea Daikin Australia $21,280 $0 Received PO-26-0919
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 14 coil Reece HVAC-R $3,332 $0 Ordered PO-26-0918
MS-BRK750 Wall bracket 750 mm heavy duty, galv 28 pr Reece HVAC-R $1,344 $0 Ordered PO-26-0918
MS-DRAIN Condensate drain 20 mm PVC + fittings 28 set Reece HVAC-R $784 $0 Ordered PO-26-0918
MS-SUND Fixings & sundries allowance 14 lot Reece HVAC-R $490 $0 Ordered PO-26-0918
EL-ISO20 Isolator 20 A 2-pole IP66 28 ea Rexel Electrical $1,008 $0 Ordered PO-26-0920
EL-IC415 Interconnect cable 4C 1.5 mm² 224 m Rexel Electrical $513 $0 Ordered PO-26-0920
Invoices$0 of $59,752
Not invoiced yet.
Timesheets — 0 hrs · $0 at cost
DateWhoHoursCostNote