WA HVAC

J-26-0221 · Kwinana — donga AC changeover

Coogee Chemicals · Kwinana — switchrooms & office · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $22,934
14 Sep 2026 → 17 Sep 2026 · order PO 4878420 · from EST-26-0283 Rev A
Budget against actualOver budget
Job value
$22,934
ex GST
Budget cost
$16,282
margin 29%
Actual to date
$16,786
70 of 72 hrs
Forecast margin
$6,148
26.8% · $504 over budget
Materials
$12,322 / $12,322
Labour
$4,464 / $3,960
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Coogee Chemicals
Site
Kwinana — switchrooms & office
Region
Kwinana
Access
Site induction · hot work permit
Site contact
Michael Tan 08 9439 8200
Lead tech
Dean Kowalski
MYOB job
J-26-0221 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXF25 Daikin 2.5 kW wall split — transportable/donga (FTXF25) 12 ea Daikin Australia $9,120 $0 Received PO-26-0885
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 6 coil Reece HVAC-R $1,428 $0 Received PO-26-0884
MS-BRK750 Wall bracket 750 mm heavy duty, galv 12 pr Reece HVAC-R $576 $0 Received PO-26-0884
MS-DRAIN Condensate drain 20 mm PVC + fittings 12 set Reece HVAC-R $336 $0 Received PO-26-0884
MS-SUND Fixings & sundries allowance 6 lot Reece HVAC-R $210 $0 Received PO-26-0884
EL-ISO20 Isolator 20 A 2-pole IP66 12 ea Rexel Electrical $432 $0 Received PO-26-0886
EL-IC415 Interconnect cable 4C 1.5 mm² 96 m Rexel Electrical $220 $0 Received PO-26-0886
Timesheets — 70 hrs · $4,464 at cost
DateWhoHoursCostNote
17 Sep 2026 Tayla Brooks 2 $76 —
17 Sep 2026 Dean Kowalski 11 $902 —
16 Sep 2026 Tayla Brooks 9 $342 —
16 Sep 2026 Dean Kowalski 11 $902 —
15 Sep 2026 Tayla Brooks 9 $342 —
15 Sep 2026 Dean Kowalski 8 $656 —
14 Sep 2026 Tayla Brooks 9 $342 Mobilise, set out
14 Sep 2026 Dean Kowalski 11 $902 Mobilise, set out