J-26-0208 · Rockingham campus — donga AC changeover

South Metropolitan TAFE · Rockingham campus · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $22,934
07 Aug 2026 → 19 Aug 2026 · order PO 4641655 · from EST-26-0275 Rev A
Budget against actualOn track
Job value
$22,934
ex GST
Budget cost
$16,282
margin 29%
Actual to date
$16,384
69 of 72 hrs
Forecast margin
$6,550
28.6% · $102 over budget
Materials
$12,322 / $12,322
Labour
$4,062 / $3,960
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
South Metropolitan TAFE
Site
Rockingham campus
Region
Rockingham
Access
Facilities sign-in · after hours preferred
Site contact
Jenny Arkell 08 9599 8600
Lead tech
Liam O'Brien
MYOB job
J-26-0208 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXF25 Daikin 2.5 kW wall split — transportable/donga (FTXF25) 12 ea Daikin Australia $9,120 $0 Received PO-26-0864
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 6 coil Reece HVAC-R $1,428 $0 Received PO-26-0863
MS-BRK750 Wall bracket 750 mm heavy duty, galv 12 pr Reece HVAC-R $576 $0 Received PO-26-0863
MS-DRAIN Condensate drain 20 mm PVC + fittings 12 set Reece HVAC-R $336 $0 Received PO-26-0863
MS-SUND Fixings & sundries allowance 6 lot Reece HVAC-R $210 $0 Received PO-26-0863
EL-ISO20 Isolator 20 A 2-pole IP66 12 ea Rexel Electrical $432 $0 Received PO-26-0865
EL-IC415 Interconnect cable 4C 1.5 mm² 96 m Rexel Electrical $220 $0 Received PO-26-0865
Timesheets — 69 hrs · $4,062 at cost
DateWhoHoursCostNote
10 Aug 2026 Tayla Brooks 1 $38 —
10 Aug 2026 Liam O'Brien 11 $814 —
10 Aug 2026 Tayla Brooks 9 $342 —
10 Aug 2026 Liam O'Brien 10 $740 —
10 Aug 2026 Tayla Brooks 10 $380 —
10 Aug 2026 Liam O'Brien 11 $814 —
07 Aug 2026 Tayla Brooks 9 $342 Mobilise, set out
07 Aug 2026 Liam O'Brien 8 $592 Mobilise, set out