J-26-0210 · Jandakot Airport — workshop exhaust & cooling

Jandakot Airport Holdings · Jandakot Airport — terminal & offices · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $41,215
04 Aug 2026 → 13 Aug 2026 · order PO 4697811 · from EST-26-0272 Rev A
Budget against actualOver budget
Job value
$41,215
ex GST
Budget cost
$28,713
margin 30%
Actual to date
$30,309
164 of 150 hrs
Forecast margin
$10,906
26.5% · $1,596 over budget
Materials
$19,629 / $19,629
Labour
$10,680 / $9,084
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Jandakot Airport Holdings
Site
Jandakot Airport — terminal & offices
Region
Jandakot
Access
Airside pass for roof access
Site contact
Sophie Lindqvist 08 9417 2000
Lead tech
Dean Kowalski
MYOB job
J-26-0210 in MYOB
Materials — from the estimate (12)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXM71 Daikin 7.1 kW wall split inverter (FTXM71) 6 ea Daikin Australia $11,340 $0 Received PO-26-0852
FT-TD250 Fantech inline mixed-flow fan 250 mm (TD-1300/250) 6 ea Fantech $4,080 $0 Received PO-26-0855
DU-FLX250 Insulated flexible duct 250 mm × 6 m 12 length Holyoake $864 $0 Received PO-26-0854
DU-SPG250 Spigot collar 250 mm with damper 12 ea Holyoake $216 $0 Received PO-26-0854
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 6 coil Reece HVAC-R $1,428 $0 Received PO-26-0851
MS-BRK750 Wall bracket 750 mm heavy duty, galv 6 pr Reece HVAC-R $288 $0 Received PO-26-0851
MS-PADS Anti-vibration pads (set of 4) 6 set Reece HVAC-R $132 $0 Received PO-26-0851
MS-DRAIN Condensate drain 20 mm PVC + fittings 6 set Reece HVAC-R $168 $0 Received PO-26-0851
MS-SUND Fixings & sundries allowance 12 lot Reece HVAC-R $420 $0 Received PO-26-0851
EL-ISO20 Isolator 20 A 2-pole IP66 12 ea Rexel Electrical $432 $0 Received PO-26-0853
EL-TPS25 2.5 mm² TPS cable × 100 m 0.6 roll Rexel Electrical $96 $0 Received PO-26-0853
EL-IC415 Interconnect cable 4C 1.5 mm² 72 m Rexel Electrical $165 $0 Received PO-26-0853
Timesheets — 164 hrs · $10,680 at cost
DateWhoHoursCostNote
10 Aug 2026 Dean Kowalski 10 $820 —
10 Aug 2026 Sam Nguyen 4 $304 —
10 Aug 2026 Tayla Brooks 11 $418 —
10 Aug 2026 Dean Kowalski 8 $656 —
10 Aug 2026 Sam Nguyen 5 $380 —
10 Aug 2026 Tayla Brooks 10 $380 —
10 Aug 2026 Dean Kowalski 9 $738 —
07 Aug 2026 Sam Nguyen 8 $608 —
07 Aug 2026 Tayla Brooks 10 $380 —
07 Aug 2026 Dean Kowalski 10 $820 —
06 Aug 2026 Sam Nguyen 6 $456 —
06 Aug 2026 Tayla Brooks 9 $342 —
06 Aug 2026 Dean Kowalski 11 $902 —
05 Aug 2026 Sam Nguyen 7 $532 —
05 Aug 2026 Tayla Brooks 8 $304 —
05 Aug 2026 Dean Kowalski 11 $902 —
04 Aug 2026 Sam Nguyen 6 $456 Mobilise, set out
04 Aug 2026 Tayla Brooks 10 $380 Mobilise, set out
04 Aug 2026 Dean Kowalski 11 $902 Mobilise, set out