Invoiced · 100% complete
Invoiced $41,215
04 Aug 2026 → 13 Aug 2026 · order PO 4697811 · from EST-26-0272 Rev A
Budget against actualOver budget
Job value
$41,215
ex GST
Budget cost
$28,713
margin 30%
Actual to date
$30,309
164 of 150 hrs
Forecast margin
$10,906
26.5% · $1,596 over budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Jandakot Airport Holdings
- Site
- Jandakot Airport — terminal & offices
- Region
- Jandakot
- Access
- Airside pass for roof access
- Site contact
- Sophie Lindqvist 08 9417 2000
- Lead tech
- Dean Kowalski
- MYOB job
- J-26-0210 in MYOB
Materials — from the estimate (12)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| DAI-FTXM71 | Daikin 7.1 kW wall split inverter (FTXM71) | 6 | ea | Daikin Australia | $11,340 | $0 | Received | PO-26-0852 | |
| FT-TD250 | Fantech inline mixed-flow fan 250 mm (TD-1300/250) | 6 | ea | Fantech | $4,080 | $0 | Received | PO-26-0855 | |
| DU-FLX250 | Insulated flexible duct 250 mm × 6 m | 12 | length | Holyoake | $864 | $0 | Received | PO-26-0854 | |
| DU-SPG250 | Spigot collar 250 mm with damper | 12 | ea | Holyoake | $216 | $0 | Received | PO-26-0854 | |
| CU-PR1438 | Pre-insulated pair coil 1/4" + 3/8" × 20 m | 6 | coil | Reece HVAC-R | $1,428 | $0 | Received | PO-26-0851 | |
| MS-BRK750 | Wall bracket 750 mm heavy duty, galv | 6 | pr | Reece HVAC-R | $288 | $0 | Received | PO-26-0851 | |
| MS-PADS | Anti-vibration pads (set of 4) | 6 | set | Reece HVAC-R | $132 | $0 | Received | PO-26-0851 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 6 | set | Reece HVAC-R | $168 | $0 | Received | PO-26-0851 | |
| MS-SUND | Fixings & sundries allowance | 12 | lot | Reece HVAC-R | $420 | $0 | Received | PO-26-0851 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 12 | ea | Rexel Electrical | $432 | $0 | Received | PO-26-0853 | |
| EL-TPS25 | 2.5 mm² TPS cable × 100 m | 0.6 | roll | Rexel Electrical | $96 | $0 | Received | PO-26-0853 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 72 | m | Rexel Electrical | $165 | $0 | Received | PO-26-0853 | |
Purchase orders (5)All POs →
Invoices$41,215 of $41,215
INV-4317 Final14 Aug 2026 · MYOB #00004317
Paid$41,215 Timesheets — 164 hrs · $10,680 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 10 Aug 2026 | Dean Kowalski | 10 | $820 | — | |
| 10 Aug 2026 | Sam Nguyen | 4 | $304 | — | |
| 10 Aug 2026 | Tayla Brooks | 11 | $418 | — | |
| 10 Aug 2026 | Dean Kowalski | 8 | $656 | — | |
| 10 Aug 2026 | Sam Nguyen | 5 | $380 | — | |
| 10 Aug 2026 | Tayla Brooks | 10 | $380 | — | |
| 10 Aug 2026 | Dean Kowalski | 9 | $738 | — | |
| 07 Aug 2026 | Sam Nguyen | 8 | $608 | — | |
| 07 Aug 2026 | Tayla Brooks | 10 | $380 | — | |
| 07 Aug 2026 | Dean Kowalski | 10 | $820 | — | |
| 06 Aug 2026 | Sam Nguyen | 6 | $456 | — | |
| 06 Aug 2026 | Tayla Brooks | 9 | $342 | — | |
| 06 Aug 2026 | Dean Kowalski | 11 | $902 | — | |
| 05 Aug 2026 | Sam Nguyen | 7 | $532 | — | |
| 05 Aug 2026 | Tayla Brooks | 8 | $304 | — | |
| 05 Aug 2026 | Dean Kowalski | 11 | $902 | — | |
| 04 Aug 2026 | Sam Nguyen | 6 | $456 | Mobilise, set out | |
| 04 Aug 2026 | Tayla Brooks | 10 | $380 | Mobilise, set out | |
| 04 Aug 2026 | Dean Kowalski | 11 | $902 | Mobilise, set out | |