WA HVAC

J-26-0203 · Jandakot Airport — rooftop unit replacement

Jandakot Airport Holdings · Jandakot Airport — terminal & offices · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $27,900
02 Aug 2026 → 08 Aug 2026 · order PO 4749283 · from EST-26-0269 Rev A
Budget against actualOn track
Job value
$27,900
ex GST
Budget cost
$21,753
margin 22%
Actual to date
$21,453
44.5 of 50 hrs
Forecast margin
$6,447
23.1% · $300 under budget
Materials
$18,705 / $18,705
Labour
$2,748 / $3,048
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Jandakot Airport Holdings
Site
Jandakot Airport — terminal & offices
Region
Jandakot
Access
Airside pass for roof access
Site contact
Sophie Lindqvist 08 9417 2000
Lead tech
Liam O'Brien
MYOB job
J-26-0203 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DU-GALV06 Galvanised sheet 0.6 mm 2400 × 1200 4 sheet BlueScope Distribution $184 $0 Received PO-26-0849
HR-EWP Scissor lift / EWP hire 2 day Coates $440 $0 Received PO-26-0850
DU-MASTIC Duct mastic & foil tape kit 2 kit Reece HVAC-R $44 $0 Received PO-26-0846
MS-SUND Fixings & sundries allowance 2 lot Reece HVAC-R $70 $0 Received PO-26-0846
EL-ISO35 Isolator 35 A 3-pole IP66 1 ea Rexel Electrical $58 $0 Received PO-26-0848
EL-5C4 4 mm² 5-core circular cable 10 m Rexel Electrical $59 $0 Received PO-26-0848
TZ-OPA303 Temperzone 30 kW packaged rooftop unit (OPA 303) 1 ea Temperzone $17,850 $0 Received PO-26-0847
Timesheets — 44.5 hrs · $2,748 at cost
DateWhoHoursCostNote
03 Aug 2026 Ben Harris 1.5 $48 —
03 Aug 2026 Liam O'Brien 8 $592 —
03 Aug 2026 Kyle Fraser 6 $408 Mobilise, set out
03 Aug 2026 Sam Nguyen 8 $608 Mobilise, set out
03 Aug 2026 Ben Harris 11 $352 Mobilise, set out
03 Aug 2026 Liam O'Brien 10 $740 Mobilise, set out