J-26-0202 · Nova operation — donga AC changeover

IGO Limited · Nova operation · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $26,054
02 Aug 2026 → 06 Aug 2026 · order PO 4877723 · from EST-26-0267 Rev A
Budget against actualOn track
Job value
$26,054
ex GST
Budget cost
$18,382
margin 29%
Actual to date
$16,404
79 of 88 hrs
Forecast margin
$9,650
37% · $1,978 under budget
Materials
$12,322 / $12,322
Labour
$4,082 / $6,060
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
IGO Limited
Site
Nova operation
Region
Fraser Range · 160 km E of Norseman
Access
FIFO 8/6 · Nova induction
Site contact
Natalie Dorsett 08 9238 8300
Lead tech
Liam O'Brien
MYOB job
J-26-0202 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXF25 Daikin 2.5 kW wall split — transportable/donga (FTXF25) 12 ea Daikin Australia $9,120 $0 Received PO-26-0861
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 6 coil Reece HVAC-R $1,428 $0 Received PO-26-0860
MS-BRK750 Wall bracket 750 mm heavy duty, galv 12 pr Reece HVAC-R $576 $0 Received PO-26-0860
MS-DRAIN Condensate drain 20 mm PVC + fittings 12 set Reece HVAC-R $336 $0 Received PO-26-0860
MS-SUND Fixings & sundries allowance 6 lot Reece HVAC-R $210 $0 Received PO-26-0860
EL-ISO20 Isolator 20 A 2-pole IP66 12 ea Rexel Electrical $432 $0 Received PO-26-0862
EL-IC415 Interconnect cable 4C 1.5 mm² 96 m Rexel Electrical $220 $0 Received PO-26-0862
Timesheets — 79 hrs · $4,082 at cost
DateWhoHoursCostNote
06 Aug 2026 Liam O'Brien 1 $74 —
05 Aug 2026 Ben Harris 10 $320 —
05 Aug 2026 Liam O'Brien 8 $592 —
04 Aug 2026 Ben Harris 10 $320 —
04 Aug 2026 Liam O'Brien 8 $592 —
03 Aug 2026 Ben Harris 11 $352 —
03 Aug 2026 Liam O'Brien 9 $666 —
03 Aug 2026 Ben Harris 11 $352 Mobilise, set out
03 Aug 2026 Liam O'Brien 11 $814 Mobilise, set out