Invoiced · 100% complete
Invoiced $31,159
10 Jul 2026 → 13 Jul 2026 · order PO 4740099 · from EST-26-0266 Rev A
Budget against actualOn track
Job value
$31,159
ex GST
Budget cost
$22,385
margin 28%
Actual to date
$22,177
107 of 102 hrs
Forecast margin
$8,983
28.8% · $208 under budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Mineral Resources
- Site
- Wodgina lithium — workshops
- Region
- Pilbara · 110 km S of Port Hedland
- Access
- FIFO · MinRes induction
- Site contact
- Jared Okafor 08 9329 3600
- Lead tech
- Dean Kowalski
- MYOB job
- J-26-0197 in MYOB
Materials — from the estimate (17)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| RG-N2-G | Dry nitrogen — G size cylinder | 0.5 | cyl | BOC Gas & Gear | $49 | $0 | Received | PO-26-0841 | |
| DU-GALV06 | Galvanised sheet 0.6 mm 2400 × 1200 | 6 | sheet | BlueScope Distribution | $276 | $0 | Received | PO-26-0842 | |
| DAI-FDYAN140 | Daikin 14.0 kW ducted split inverter, 1-ph (FDYAN140) | 2 | ea | Daikin Australia | $11,300 | $0 | Received | PO-26-0838 | |
| CT-BRC1H | Daikin wired controller (BRC1H) | 2 | ea | Daikin Australia | $440 | $0 | Received | PO-26-0838 | |
| DU-FLX250 | Insulated flexible duct 250 mm × 6 m | 12 | length | Holyoake | $864 | $0 | Received | PO-26-0840 | |
| DU-DIF450 | Ceiling diffuser 4-way 450 sq. with plenum | 12 | ea | Holyoake | $552 | $0 | Received | PO-26-0840 | |
| DU-RAG600 | Return air grille 600 × 600 with filter | 2 | ea | Holyoake | $148 | $0 | Received | PO-26-0840 | |
| DU-SPG250 | Spigot collar 250 mm with damper | 12 | ea | Holyoake | $216 | $0 | Received | PO-26-0840 | |
| DU-VCD300 | Volume control damper 300 × 300 | 1 | ea | Holyoake | $48 | $0 | Received | PO-26-0840 | |
| CU-PR3858 | Pre-insulated pair coil 3/8" + 5/8" × 20 m | 2 | coil | Reece HVAC-R | $684 | $0 | Received | PO-26-0837 | |
| INS-DUCTR1 | Duct insulation blanket R1.0 × 15 m roll | 2 | roll | Reece HVAC-R | $224 | $0 | Received | PO-26-0837 | |
| DU-MASTIC | Duct mastic & foil tape kit | 6 | kit | Reece HVAC-R | $132 | $0 | Received | PO-26-0837 | |
| MS-PADS | Anti-vibration pads (set of 4) | 2 | set | Reece HVAC-R | $44 | $0 | Received | PO-26-0837 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 2 | set | Reece HVAC-R | $56 | $0 | Received | PO-26-0837 | |
| MS-SUND | Fixings & sundries allowance | 3 | lot | Reece HVAC-R | $105 | $0 | Received | PO-26-0837 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 2 | ea | Rexel Electrical | $72 | $0 | Received | PO-26-0839 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 50 | m | Rexel Electrical | $115 | $0 | Received | PO-26-0839 | |
Purchase orders (6)All POs →
Invoices$31,159 of $31,159
INV-4303 Final14 Jul 2026 · MYOB #00004303
Paid$31,159 Timesheets — 107 hrs · $6,852 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 13 Jul 2026 | Kyle Fraser | 0 | $0 | — | |
| 13 Jul 2026 | Sam Nguyen | 0 | $0 | — | |
| 13 Jul 2026 | Ben Harris | 1 | $32 | — | |
| 13 Jul 2026 | Dean Kowalski | 8 | $656 | — | |
| 13 Jul 2026 | Kyle Fraser | 5 | $340 | — | |
| 13 Jul 2026 | Sam Nguyen | 7 | $532 | — | |
| 13 Jul 2026 | Ben Harris | 9 | $288 | — | |
| 13 Jul 2026 | Dean Kowalski | 10 | $820 | — | |
| 13 Jul 2026 | Kyle Fraser | 7 | $476 | — | |
| 13 Jul 2026 | Sam Nguyen | 6 | $456 | — | |
| 13 Jul 2026 | Ben Harris | 11 | $352 | — | |
| 13 Jul 2026 | Dean Kowalski | 9 | $738 | — | |
| 10 Jul 2026 | Kyle Fraser | 6 | $408 | Mobilise, set out | |
| 10 Jul 2026 | Sam Nguyen | 7 | $532 | Mobilise, set out | |
| 10 Jul 2026 | Ben Harris | 10 | $320 | Mobilise, set out | |
| 10 Jul 2026 | Dean Kowalski | 11 | $902 | Mobilise, set out | |