J-26-0196 · Kwinana fabrication facility — crib room wall splits

Monadelphous Engineering · Kwinana fabrication facility · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $12,601
15 Jul 2026 → 20 Jul 2026 · order PO 4729647 · from EST-26-0265 Rev A
Budget against actualOn track
Job value
$12,601
ex GST
Budget cost
$9,079
margin 28%
Actual to date
$9,025
33 of 36 hrs
Forecast margin
$3,576
28.4% · $54 under budget
Materials
$6,973 / $6,973
Labour
$2,052 / $2,106
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Monadelphous Engineering
Site
Kwinana fabrication facility
Region
Kwinana
Access
Site induction · PPE
Site contact
Craig Ellery 08 9316 1255
Lead tech
Ryan Teo
MYOB job
J-26-0196 in MYOB
Materials — from the estimate (8)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXM71 Daikin 7.1 kW wall split inverter (FTXM71) 3 ea Daikin Australia $5,670 $0 Received PO-26-0844
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 3 coil Reece HVAC-R $714 $0 Received PO-26-0843
MS-BRK750 Wall bracket 750 mm heavy duty, galv 3 pr Reece HVAC-R $144 $0 Received PO-26-0843
MS-PADS Anti-vibration pads (set of 4) 3 set Reece HVAC-R $66 $0 Received PO-26-0843
MS-DRAIN Condensate drain 20 mm PVC + fittings 3 set Reece HVAC-R $84 $0 Received PO-26-0843
MS-SUND Fixings & sundries allowance 3 lot Reece HVAC-R $105 $0 Received PO-26-0843
EL-ISO20 Isolator 20 A 2-pole IP66 3 ea Rexel Electrical $108 $0 Received PO-26-0845
EL-IC415 Interconnect cable 4C 1.5 mm² 36 m Rexel Electrical $82 $0 Received PO-26-0845
Timesheets — 33 hrs · $2,052 at cost
DateWhoHoursCostNote
16 Jul 2026 Sam Nguyen 0 $0 —
16 Jul 2026 Tayla Brooks 1 $38 —
16 Jul 2026 Ryan Teo 11 $792 —
15 Jul 2026 Sam Nguyen 4 $304 Mobilise, set out
15 Jul 2026 Tayla Brooks 9 $342 Mobilise, set out
15 Jul 2026 Ryan Teo 8 $576 Mobilise, set out