WA HVAC

J-26-0186 · Roy Hill mine — donga AC changeover

Roy Hill Holdings · Roy Hill mine — process plant · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $25,722
04 Jul 2026 → 07 Jul 2026 · order PO 4850515 · from EST-26-0259 Rev A
Budget against actualOn track
Job value
$25,722
ex GST
Budget cost
$18,116
margin 30%
Actual to date
$16,938
83 of 88 hrs
Forecast margin
$8,784
34.1% · $1,178 under budget
Materials
$12,322 / $12,056
Labour
$4,616 / $6,060
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Roy Hill Holdings
Site
Roy Hill mine — process plant
Region
Pilbara · 115 km N of Newman
Access
FIFO 8/6 · Roy Hill induction + Silica awareness
Site contact
Brendan Clancy 08 6142 4000
Lead tech
Ryan Teo
MYOB job
J-26-0186 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXF25 Daikin 2.5 kW wall split — transportable/donga (FTXF25) 12 ea Daikin Australia $8,854 $0 Received PO-26-0820
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 6 coil Reece HVAC-R $1,428 $0 Received PO-26-0819
MS-BRK750 Wall bracket 750 mm heavy duty, galv 12 pr Reece HVAC-R $576 $0 Received PO-26-0819
MS-DRAIN Condensate drain 20 mm PVC + fittings 12 set Reece HVAC-R $336 $0 Received PO-26-0819
MS-SUND Fixings & sundries allowance 6 lot Reece HVAC-R $210 $0 Received PO-26-0819
EL-ISO20 Isolator 20 A 2-pole IP66 12 ea Rexel Electrical $432 $0 Received PO-26-0821
EL-IC415 Interconnect cable 4C 1.5 mm² 96 m Rexel Electrical $220 $0 Received PO-26-0821
Timesheets — 83 hrs · $4,616 at cost
DateWhoHoursCostNote
07 Jul 2026 Ryan Teo 4 $288 —
07 Jul 2026 Tayla Brooks 10 $380 —
07 Jul 2026 Ryan Teo 11 $792 —
06 Jul 2026 Tayla Brooks 9 $342 —
06 Jul 2026 Ryan Teo 11 $792 —
06 Jul 2026 Tayla Brooks 10 $380 —
06 Jul 2026 Ryan Teo 8 $576 —
06 Jul 2026 Tayla Brooks 11 $418 Mobilise, set out
06 Jul 2026 Ryan Teo 9 $648 Mobilise, set out