Invoiced · 100% complete
Invoiced $30,321
24 May 2026 → 04 Jun 2026 · order PO 4442765 · from EST-26-0253 Rev A
Budget against actualOn track
Job value
$30,321
ex GST
Budget cost
$21,022
margin 31%
Actual to date
$20,671
129.5 of 116 hrs
Forecast margin
$9,651
31.8% · $351 under budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- IGO Limited
- Site
- Nova operation
- Region
- Fraser Range · 160 km E of Norseman
- Access
- FIFO 8/6 · Nova induction
- Site contact
- Natalie Dorsett 08 9238 8300
- Lead tech
- Liam O'Brien
- MYOB job
- J-26-0178 in MYOB
Materials — from the estimate (12)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| DAI-FTXM71 | Daikin 7.1 kW wall split inverter (FTXM71) | 4 | ea | Daikin Australia | $7,340 | $0 | Received | PO-26-0788 | |
| FT-TD250 | Fantech inline mixed-flow fan 250 mm (TD-1300/250) | 4 | ea | Fantech | $2,720 | $0 | Received | PO-26-0791 | |
| DU-FLX250 | Insulated flexible duct 250 mm × 6 m | 8 | length | Holyoake | $576 | $0 | Received | PO-26-0790 | |
| DU-SPG250 | Spigot collar 250 mm with damper | 8 | ea | Holyoake | $144 | $0 | Received | PO-26-0790 | |
| CU-PR1438 | Pre-insulated pair coil 1/4" + 3/8" × 20 m | 4 | coil | Reece HVAC-R | $952 | $0 | Received | PO-26-0787 | |
| MS-BRK750 | Wall bracket 750 mm heavy duty, galv | 4 | pr | Reece HVAC-R | $192 | $0 | Received | PO-26-0787 | |
| MS-PADS | Anti-vibration pads (set of 4) | 4 | set | Reece HVAC-R | $88 | $0 | Received | PO-26-0787 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 4 | set | Reece HVAC-R | $112 | $0 | Received | PO-26-0787 | |
| MS-SUND | Fixings & sundries allowance | 8 | lot | Reece HVAC-R | $280 | $0 | Received | PO-26-0787 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 8 | ea | Rexel Electrical | $288 | $0 | Received | PO-26-0789 | |
| EL-TPS25 | 2.5 mm² TPS cable × 100 m | 0.4 | roll | Rexel Electrical | $64 | $0 | Received | PO-26-0789 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 48 | m | Rexel Electrical | $110 | $0 | Received | PO-26-0789 | |
Purchase orders (5)All POs →
Invoices$30,321 of $30,321
INV-4284 Final05 Jun 2026 · MYOB #00004284
Paid$30,321 Timesheets — 129.5 hrs · $7,805 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 29 May 2026 | Sam Nguyen | 0 | $0 | — | |
| 29 May 2026 | Tayla Brooks | 0 | $0 | — | |
| 29 May 2026 | Liam O'Brien | 0.5 | $37 | — | |
| 28 May 2026 | Sam Nguyen | 5 | $380 | — | |
| 28 May 2026 | Tayla Brooks | 11 | $418 | — | |
| 28 May 2026 | Liam O'Brien | 11 | $814 | — | |
| 27 May 2026 | Sam Nguyen | 4 | $304 | — | |
| 27 May 2026 | Tayla Brooks | 10 | $380 | — | |
| 27 May 2026 | Liam O'Brien | 11 | $814 | — | |
| 26 May 2026 | Sam Nguyen | 6 | $456 | — | |
| 26 May 2026 | Tayla Brooks | 11 | $418 | — | |
| 26 May 2026 | Liam O'Brien | 10 | $740 | — | |
| 25 May 2026 | Sam Nguyen | 8 | $608 | — | |
| 25 May 2026 | Tayla Brooks | 11 | $418 | — | |
| 25 May 2026 | Liam O'Brien | 9 | $666 | — | |
| 25 May 2026 | Sam Nguyen | 6 | $456 | Mobilise, set out | |
| 25 May 2026 | Tayla Brooks | 8 | $304 | Mobilise, set out | |
| 25 May 2026 | Liam O'Brien | 8 | $592 | Mobilise, set out | |