J-26-0165 · St Ives gold mine — donga AC changeover

Gold Fields Australia · St Ives gold mine — admin & crib rooms · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $25,722
07 May 2026 → 14 May 2026 · order PO 4418047 · from EST-26-0245 Rev A
Budget against actualOn track
Job value
$25,722
ex GST
Budget cost
$18,116
margin 30%
Actual to date
$16,759
83.5 of 88 hrs
Forecast margin
$8,963
34.8% · $1,357 under budget
Materials
$12,056 / $12,056
Labour
$4,703 / $6,060
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Gold Fields Australia
Site
St Ives gold mine — admin & crib rooms
Region
Goldfields · Kambalda
Access
DIDO · St Ives induction
Site contact
Tom Ferreira 08 9211 9200
Lead tech
Ryan Teo
MYOB job
J-26-0165 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXF25 Daikin 2.5 kW wall split — transportable/donga (FTXF25) 12 ea Daikin Australia $8,854 $0 Received PO-26-0776
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 6 coil Reece HVAC-R $1,428 $0 Received PO-26-0775
MS-BRK750 Wall bracket 750 mm heavy duty, galv 12 pr Reece HVAC-R $576 $0 Received PO-26-0775
MS-DRAIN Condensate drain 20 mm PVC + fittings 12 set Reece HVAC-R $336 $0 Received PO-26-0775
MS-SUND Fixings & sundries allowance 6 lot Reece HVAC-R $210 $0 Received PO-26-0775
EL-ISO20 Isolator 20 A 2-pole IP66 12 ea Rexel Electrical $432 $0 Received PO-26-0777
EL-IC415 Interconnect cable 4C 1.5 mm² 96 m Rexel Electrical $220 $0 Received PO-26-0777
Timesheets — 83.5 hrs · $4,703 at cost
DateWhoHoursCostNote
11 May 2026 Tayla Brooks 6.5 $247 —
11 May 2026 Ryan Teo 10 $720 —
11 May 2026 Tayla Brooks 8 $304 —
11 May 2026 Ryan Teo 8 $576 —
11 May 2026 Tayla Brooks 8 $304 —
11 May 2026 Ryan Teo 8 $576 —
08 May 2026 Tayla Brooks 8 $304 —
08 May 2026 Ryan Teo 11 $792 —
07 May 2026 Tayla Brooks 8 $304 Mobilise, set out
07 May 2026 Ryan Teo 8 $576 Mobilise, set out