WA HVAC

J-26-0162 · Kambalda Village — coolroom refrigeration

Civeo · Kambalda Village · Refrigeration
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $14,511
09 May 2026 → 14 May 2026 · order PO 4800186 · from EST-26-0244 Rev A
Budget against actualOn track
Job value
$14,511
ex GST
Budget cost
$10,098
margin 30%
Actual to date
$9,440
61 of 56 hrs
Forecast margin
$5,071
34.9% · $658 under budget
Materials
$5,714 / $5,714
Labour
$3,726 / $4,384
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Civeo
Site
Kambalda Village
Region
Goldfields · Kambalda
Access
Drive-in · village reception
Site contact
Shane Mathers 08 9473 1800
Lead tech
Ryan Teo
MYOB job
J-26-0162 in MYOB
Materials — from the estimate (13)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
RG-R448-10 Refrigerant R448A — 10 kg cylinder 0.6 cyl Actrol $343 $0 Received PO-26-0779
RG-N2-G Dry nitrogen — G size cylinder 0.5 cyl BOC Gas & Gear $49 $0 Received PO-26-0783
RG-BRZ15 Silver brazing rod 15% — 1 kg 0.25 pack BOC Gas & Gear $41 $0 Received PO-26-0783
HC-LET068 Heatcraft condensing unit 1.5 HP medium temp (R448A) 1 ea Heatcraft Australia $3,180 $0 Received PO-26-0781
KB-EVMT26 Kirby coolroom evaporator, medium temp 2.6 kW 1 ea Kirby Refrigeration $1,240 $0 Received PO-26-0780
CT-XR60 Dixell XR60CX coolroom controller kit 1 ea Kirby Refrigeration $310 $0 Received PO-26-0780
CU-C38-15 Copper tube 3/8" soft coil × 15 m 1 coil Reece HVAC-R $108 $0 Received PO-26-0778
CU-C58-15 Copper tube 5/8" soft coil × 15 m 1 coil Reece HVAC-R $188 $0 Received PO-26-0778
CU-FIT-PK Copper fittings pack — elbows, couplers, tees 1 pack Reece HVAC-R $58 $0 Received PO-26-0778
INS-AF58 Armaflex 5/8" ID × 19 mm × 1.8 m 8 length Reece HVAC-R $80 $0 Received PO-26-0778
MS-SUND Fixings & sundries allowance 1 lot Reece HVAC-R $35 $0 Received PO-26-0778
EL-ISO20 Isolator 20 A 2-pole IP66 1 ea Rexel Electrical $36 $0 Received PO-26-0782
EL-IC415 Interconnect cable 4C 1.5 mm² 20 m Rexel Electrical $46 $0 Received PO-26-0782
Timesheets — 61 hrs · $3,726 at cost
DateWhoHoursCostNote
11 May 2026 Sam Nguyen 0 $0 —
11 May 2026 Tayla Brooks 3 $114 —
11 May 2026 Ryan Teo 11 $792 —
11 May 2026 Sam Nguyen 6 $456 —
11 May 2026 Tayla Brooks 9 $342 —
11 May 2026 Ryan Teo 8 $576 —
11 May 2026 Sam Nguyen 6 $456 Mobilise, set out
11 May 2026 Tayla Brooks 9 $342 Mobilise, set out
11 May 2026 Ryan Teo 9 $648 Mobilise, set out