WA HVAC

J-26-0160 · Nova operation — admin building ducted AC replacement

IGO Limited · Nova operation · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $58,362
26 Apr 2026 → 08 May 2026 · order PO 4723887 · from EST-26-0242 Rev A
Budget against actualOver budget
Job value
$58,362
ex GST
Budget cost
$41,985
margin 28%
Actual to date
$43,757
218 of 188 hrs
Forecast margin
$14,605
25% · $1,772 over budget
Materials
$29,965 / $29,965
Labour
$13,792 / $12,020
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
IGO Limited
Site
Nova operation
Region
Fraser Range · 160 km E of Norseman
Access
FIFO 8/6 · Nova induction
Site contact
Natalie Dorsett 08 9238 8300
Lead tech
Liam O'Brien
MYOB job
J-26-0160 in MYOB
Materials — from the estimate (17)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
RG-N2-G Dry nitrogen — G size cylinder 1 cyl BOC Gas & Gear $98 $0 Received PO-26-0764
DU-GALV06 Galvanised sheet 0.6 mm 2400 × 1200 12 sheet BlueScope Distribution $552 $0 Received PO-26-0765
DAI-FDYAN140 Daikin 14.0 kW ducted split inverter, 1-ph (FDYAN140) 4 ea Daikin Australia $21,942 $0 Received PO-26-0761
CT-BRC1H Daikin wired controller (BRC1H) 4 ea Daikin Australia $854 $0 Received PO-26-0761
DU-FLX250 Insulated flexible duct 250 mm × 6 m 24 length Holyoake $1,728 $0 Received PO-26-0763
DU-DIF450 Ceiling diffuser 4-way 450 sq. with plenum 24 ea Holyoake $1,104 $0 Received PO-26-0763
DU-RAG600 Return air grille 600 × 600 with filter 4 ea Holyoake $296 $0 Received PO-26-0763
DU-SPG250 Spigot collar 250 mm with damper 24 ea Holyoake $432 $0 Received PO-26-0763
DU-VCD300 Volume control damper 300 × 300 2 ea Holyoake $96 $0 Received PO-26-0763
CU-PR3858 Pre-insulated pair coil 3/8" + 5/8" × 20 m 4 coil Reece HVAC-R $1,368 $0 Received PO-26-0760
INS-DUCTR1 Duct insulation blanket R1.0 × 15 m roll 4 roll Reece HVAC-R $448 $0 Received PO-26-0760
DU-MASTIC Duct mastic & foil tape kit 12 kit Reece HVAC-R $264 $0 Received PO-26-0760
MS-PADS Anti-vibration pads (set of 4) 4 set Reece HVAC-R $88 $0 Received PO-26-0760
MS-DRAIN Condensate drain 20 mm PVC + fittings 4 set Reece HVAC-R $112 $0 Received PO-26-0760
MS-SUND Fixings & sundries allowance 6 lot Reece HVAC-R $210 $0 Received PO-26-0760
EL-ISO20 Isolator 20 A 2-pole IP66 4 ea Rexel Electrical $144 $0 Received PO-26-0762
EL-IC415 Interconnect cable 4C 1.5 mm² 100 m Rexel Electrical $229 $0 Received PO-26-0762
Timesheets — 218 hrs · $13,792 at cost
DateWhoHoursCostNote
04 May 2026 Sam Nguyen 7 $532 —
04 May 2026 Tayla Brooks 8 $304 —
04 May 2026 Liam O'Brien 9 $666 —
01 May 2026 Kyle Fraser 6 $408 —
01 May 2026 Sam Nguyen 7 $532 —
01 May 2026 Tayla Brooks 10 $380 —
01 May 2026 Liam O'Brien 10 $740 —
30 Apr 2026 Kyle Fraser 8 $544 —
30 Apr 2026 Sam Nguyen 8 $608 —
30 Apr 2026 Tayla Brooks 8 $304 —
30 Apr 2026 Liam O'Brien 9 $666 —
29 Apr 2026 Kyle Fraser 8 $544 —
29 Apr 2026 Sam Nguyen 7 $532 —
29 Apr 2026 Tayla Brooks 8 $304 —
29 Apr 2026 Liam O'Brien 11 $814 —
28 Apr 2026 Kyle Fraser 7 $476 —
28 Apr 2026 Sam Nguyen 6 $456 —
28 Apr 2026 Tayla Brooks 8 $304 —
28 Apr 2026 Liam O'Brien 11 $814 —
27 Apr 2026 Kyle Fraser 4 $272 —
27 Apr 2026 Sam Nguyen 8 $608 —
27 Apr 2026 Tayla Brooks 9 $342 —
27 Apr 2026 Liam O'Brien 9 $666 —
27 Apr 2026 Kyle Fraser 7 $476 Mobilise, set out
27 Apr 2026 Sam Nguyen 5 $380 Mobilise, set out
27 Apr 2026 Tayla Brooks 10 $380 Mobilise, set out
27 Apr 2026 Liam O'Brien 10 $740 Mobilise, set out