WA HVAC

J-26-0149 · Kambalda Village — crib room wall splits

Civeo · Kambalda Village · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $15,473
25 Mar 2026 → 06 Apr 2026 · order PO 4621894 · from EST-26-0234 Rev A
Budget against actualOn track
Job value
$15,473
ex GST
Budget cost
$10,984
margin 29%
Actual to date
$9,804
49 of 52 hrs
Forecast margin
$5,669
36.6% · $1,179 under budget
Materials
$6,808 / $6,778
Labour
$2,996 / $4,206
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Civeo
Site
Kambalda Village
Region
Goldfields · Kambalda
Access
Drive-in · village reception
Site contact
Shane Mathers 08 9473 1800
Lead tech
Liam O'Brien
MYOB job
J-26-0149 in MYOB
Materials — from the estimate (8)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DAI-FTXM71 Daikin 7.1 kW wall split inverter (FTXM71) 3 ea Daikin Australia $5,505 $0 Received PO-26-0745
CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m 3 coil Reece HVAC-R $683 $0 Received PO-26-0744
MS-BRK750 Wall bracket 750 mm heavy duty, galv 3 pr Reece HVAC-R $144 $0 Received PO-26-0744
MS-PADS Anti-vibration pads (set of 4) 3 set Reece HVAC-R $66 $0 Received PO-26-0744
MS-DRAIN Condensate drain 20 mm PVC + fittings 3 set Reece HVAC-R $84 $0 Received PO-26-0744
MS-SUND Fixings & sundries allowance 3 lot Reece HVAC-R $105 $0 Received PO-26-0744
EL-ISO20 Isolator 20 A 2-pole IP66 3 ea Rexel Electrical $108 $0 Received PO-26-0746
EL-IC415 Interconnect cable 4C 1.5 mm² 36 m Rexel Electrical $82 $0 Received PO-26-0746
Timesheets — 49 hrs · $2,996 at cost
DateWhoHoursCostNote
27 Mar 2026 Liam O'Brien 4 $296 —
26 Mar 2026 Sam Nguyen 4 $304 —
26 Mar 2026 Tayla Brooks 8 $304 —
26 Mar 2026 Liam O'Brien 8 $592 —
25 Mar 2026 Sam Nguyen 5 $380 Mobilise, set out
25 Mar 2026 Tayla Brooks 10 $380 Mobilise, set out
25 Mar 2026 Liam O'Brien 10 $740 Mobilise, set out