J-26-0146 · Civic Centre — camp kitchen refrigeration

City of Cockburn · Civic Centre — Spearwood · Refrigeration
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $58,618
14 Mar 2026 → 21 Mar 2026 · order PO 4856243 · from EST-26-0232 Rev A
Budget against actualOn track
Job value
$58,618
ex GST
Budget cost
$41,630
margin 29%
Actual to date
$41,624
176 of 188 hrs
Forecast margin
$16,994
29% · $6 under budget
Materials
$30,942 / $30,870
Labour
$10,682 / $10,760
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
City of Cockburn
Site
Civic Centre — Spearwood
Region
Spearwood
Access
Reception sign-in
Site contact
Neil Harcourt 08 9411 3444
Lead tech
Ryan Teo
MYOB job
J-26-0146 in MYOB
Materials — from the estimate (18)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
RG-R448-10 Refrigerant R448A — 10 kg cylinder 3.2 cyl Actrol $1,829 $0 Received PO-26-0720
RG-N2-G Dry nitrogen — G size cylinder 2 cyl BOC Gas & Gear $196 $0 Received PO-26-0724
RG-BRZ15 Silver brazing rod 15% — 1 kg 1.3 pack BOC Gas & Gear $215 $0 Received PO-26-0724
HC-LET068 Heatcraft condensing unit 1.5 HP medium temp (R448A) 2 ea Heatcraft Australia $6,360 $0 Received PO-26-0722
HC-LET150 Heatcraft condensing unit 3.5 HP low temp (R448A) 2 ea Heatcraft Australia $11,920 $0 Received PO-26-0722
KB-EVMT26 Kirby coolroom evaporator, medium temp 2.6 kW 2 ea Kirby Refrigeration $2,480 $0 Received PO-26-0721
KB-EVLT30 Kirby freezer evaporator, low temp 3.0 kW electric defrost 2 ea Kirby Refrigeration $3,960 $0 Received PO-26-0721
CT-XR60 Dixell XR60CX coolroom controller kit 4 ea Kirby Refrigeration $1,240 $0 Received PO-26-0721
CU-C38-15 Copper tube 3/8" soft coil × 15 m 4 coil Reece HVAC-R $413 $0 Received PO-26-0719
CU-C58-15 Copper tube 5/8" soft coil × 15 m 2 coil Reece HVAC-R $360 $0 Received PO-26-0719
CU-H78-58 Copper tube 7/8" hard drawn × 5.8 m 4 length Reece HVAC-R $490 $0 Received PO-26-0719
CU-FIT-PK Copper fittings pack — elbows, couplers, tees 6 pack Reece HVAC-R $333 $0 Received PO-26-0719
INS-AF58 Armaflex 5/8" ID × 19 mm × 1.8 m 36 length Reece HVAC-R $360 $0 Received PO-26-0719
MS-SUND Fixings & sundries allowance 4 lot Reece HVAC-R $140 $0 Received PO-26-0719
EL-ISO20 Isolator 20 A 2-pole IP66 2 ea Rexel Electrical $72 $0 Received PO-26-0723
EL-ISO35 Isolator 35 A 3-pole IP66 2 ea Rexel Electrical $116 $0 Received PO-26-0723
EL-IC415 Interconnect cable 4C 1.5 mm² 40 m Rexel Electrical $92 $0 Received PO-26-0723
EL-5C4 4 mm² 5-core circular cable 50 m Rexel Electrical $295 $0 Received PO-26-0723
Timesheets — 176 hrs · $10,682 at cost
DateWhoHoursCostNote
23 Mar 2026 Sam Nguyen 0 $0 —
23 Mar 2026 Tayla Brooks 0 $0 —
23 Mar 2026 Ryan Teo 8 $576 —
20 Mar 2026 Sam Nguyen 5 $380 —
20 Mar 2026 Tayla Brooks 8 $304 —
20 Mar 2026 Ryan Teo 11 $792 —
19 Mar 2026 Sam Nguyen 6 $456 —
19 Mar 2026 Tayla Brooks 9 $342 —
19 Mar 2026 Ryan Teo 8 $576 —
18 Mar 2026 Sam Nguyen 5 $380 —
18 Mar 2026 Tayla Brooks 9 $342 —
18 Mar 2026 Ryan Teo 8 $576 —
17 Mar 2026 Sam Nguyen 5 $380 —
17 Mar 2026 Tayla Brooks 11 $418 —
17 Mar 2026 Ryan Teo 11 $792 —
16 Mar 2026 Sam Nguyen 4 $304 —
16 Mar 2026 Tayla Brooks 9 $342 —
16 Mar 2026 Ryan Teo 10 $720 —
16 Mar 2026 Sam Nguyen 5 $380 —
16 Mar 2026 Tayla Brooks 8 $304 —
16 Mar 2026 Ryan Teo 11 $792 —
16 Mar 2026 Sam Nguyen 8 $608 Mobilise, set out
16 Mar 2026 Tayla Brooks 9 $342 Mobilise, set out
16 Mar 2026 Ryan Teo 8 $576 Mobilise, set out