Invoiced · 100% complete
Invoiced $29,309
15 Mar 2026 → 18 Mar 2026 · order PO 4867920 · from EST-26-0230 Rev A
Budget against actualOver budget
Job value
$29,309
ex GST
Budget cost
$20,815
margin 29%
Actual to date
$21,479
105.5 of 94 hrs
Forecast margin
$7,830
26.7% · $664 over budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Jandakot Airport Holdings
- Site
- Jandakot Airport — terminal & offices
- Region
- Jandakot
- Access
- Airside pass for roof access
- Site contact
- Sophie Lindqvist 08 9417 2000
- Lead tech
- Ryan Teo
- MYOB job
- J-26-0141 in MYOB
Materials — from the estimate (18)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| RG-R448-10 | Refrigerant R448A — 10 kg cylinder | 1.6 | cyl | Actrol | $914 | $0 | Received | PO-26-0726 | |
| RG-N2-G | Dry nitrogen — G size cylinder | 1 | cyl | BOC Gas & Gear | $98 | $0 | Received | PO-26-0730 | |
| RG-BRZ15 | Silver brazing rod 15% — 1 kg | 0.65 | pack | BOC Gas & Gear | $107 | $0 | Received | PO-26-0730 | |
| HC-LET068 | Heatcraft condensing unit 1.5 HP medium temp (R448A) | 1 | ea | Heatcraft Australia | $3,180 | $0 | Received | PO-26-0728 | |
| HC-LET150 | Heatcraft condensing unit 3.5 HP low temp (R448A) | 1 | ea | Heatcraft Australia | $5,960 | $0 | Received | PO-26-0728 | |
| KB-EVMT26 | Kirby coolroom evaporator, medium temp 2.6 kW | 1 | ea | Kirby Refrigeration | $1,240 | $0 | Received | PO-26-0727 | |
| KB-EVLT30 | Kirby freezer evaporator, low temp 3.0 kW electric defrost | 1 | ea | Kirby Refrigeration | $1,980 | $0 | Received | PO-26-0727 | |
| CT-XR60 | Dixell XR60CX coolroom controller kit | 2 | ea | Kirby Refrigeration | $620 | $0 | Received | PO-26-0727 | |
| CU-C38-15 | Copper tube 3/8" soft coil × 15 m | 2 | coil | Reece HVAC-R | $207 | $0 | Received | PO-26-0725 | |
| CU-C58-15 | Copper tube 5/8" soft coil × 15 m | 1 | coil | Reece HVAC-R | $180 | $0 | Received | PO-26-0725 | |
| CU-H78-58 | Copper tube 7/8" hard drawn × 5.8 m | 2 | length | Reece HVAC-R | $245 | $0 | Received | PO-26-0725 | |
| CU-FIT-PK | Copper fittings pack — elbows, couplers, tees | 3 | pack | Reece HVAC-R | $167 | $0 | Received | PO-26-0725 | |
| INS-AF58 | Armaflex 5/8" ID × 19 mm × 1.8 m | 18 | length | Reece HVAC-R | $180 | $0 | Received | PO-26-0725 | |
| MS-SUND | Fixings & sundries allowance | 2 | lot | Reece HVAC-R | $70 | $0 | Received | PO-26-0725 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 1 | ea | Rexel Electrical | $36 | $0 | Received | PO-26-0729 | |
| EL-ISO35 | Isolator 35 A 3-pole IP66 | 1 | ea | Rexel Electrical | $58 | $0 | Received | PO-26-0729 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 20 | m | Rexel Electrical | $46 | $0 | Received | PO-26-0729 | |
| EL-5C4 | 4 mm² 5-core circular cable | 25 | m | Rexel Electrical | $148 | $0 | Received | PO-26-0729 | |
Purchase orders (6)All POs →
Invoices$29,309 of $29,309
INV-4249 Final19 Mar 2026 · MYOB #00004249
Paid$29,309 Timesheets — 105.5 hrs · $6,008 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 18 Mar 2026 | Sam Nguyen | 0 | $0 | — | |
| 18 Mar 2026 | Ben Harris | 0.5 | $16 | — | |
| 18 Mar 2026 | Ryan Teo | 9 | $648 | — | |
| 18 Mar 2026 | Sam Nguyen | 5 | $380 | — | |
| 18 Mar 2026 | Ben Harris | 11 | $352 | — | |
| 18 Mar 2026 | Ryan Teo | 11 | $792 | — | |
| 17 Mar 2026 | Sam Nguyen | 4 | $304 | — | |
| 17 Mar 2026 | Ben Harris | 11 | $352 | — | |
| 17 Mar 2026 | Ryan Teo | 9 | $648 | — | |
| 16 Mar 2026 | Sam Nguyen | 4 | $304 | — | |
| 16 Mar 2026 | Ben Harris | 11 | $352 | — | |
| 16 Mar 2026 | Ryan Teo | 8 | $576 | — | |
| 16 Mar 2026 | Sam Nguyen | 5 | $380 | Mobilise, set out | |
| 16 Mar 2026 | Ben Harris | 8 | $256 | Mobilise, set out | |
| 16 Mar 2026 | Ryan Teo | 9 | $648 | Mobilise, set out | |