Invoiced · 100% complete
Invoiced $32,429
25 Feb 2026 → 09 Mar 2026 · order PO 4625135 · from EST-26-0229 Rev A
Budget against actualOn track
Job value
$32,429
ex GST
Budget cost
$22,915
margin 29%
Actual to date
$22,023
112 of 110 hrs
Forecast margin
$10,406
32.1% · $892 under budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- IGO Limited
- Site
- Nova operation
- Region
- Fraser Range · 160 km E of Norseman
- Access
- FIFO 8/6 · Nova induction
- Site contact
- Natalie Dorsett 08 9238 8300
- Lead tech
- Craig Whitfield
- MYOB job
- J-26-0139 in MYOB
Materials — from the estimate (18)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| RG-R448-10 | Refrigerant R448A — 10 kg cylinder | 1.6 | cyl | Actrol | $914 | $0 | Received | PO-26-0708 | |
| RG-N2-G | Dry nitrogen — G size cylinder | 1 | cyl | BOC Gas & Gear | $98 | $0 | Received | PO-26-0712 | |
| RG-BRZ15 | Silver brazing rod 15% — 1 kg | 0.65 | pack | BOC Gas & Gear | $107 | $0 | Received | PO-26-0712 | |
| HC-LET068 | Heatcraft condensing unit 1.5 HP medium temp (R448A) | 1 | ea | Heatcraft Australia | $3,180 | $0 | Received | PO-26-0710 | |
| HC-LET150 | Heatcraft condensing unit 3.5 HP low temp (R448A) | 1 | ea | Heatcraft Australia | $5,960 | $0 | Received | PO-26-0710 | |
| KB-EVMT26 | Kirby coolroom evaporator, medium temp 2.6 kW | 1 | ea | Kirby Refrigeration | $1,240 | $0 | Received | PO-26-0709 | |
| KB-EVLT30 | Kirby freezer evaporator, low temp 3.0 kW electric defrost | 1 | ea | Kirby Refrigeration | $1,980 | $0 | Received | PO-26-0709 | |
| CT-XR60 | Dixell XR60CX coolroom controller kit | 2 | ea | Kirby Refrigeration | $620 | $0 | Received | PO-26-0709 | |
| CU-C38-15 | Copper tube 3/8" soft coil × 15 m | 2 | coil | Reece HVAC-R | $207 | $0 | Received | PO-26-0707 | |
| CU-C58-15 | Copper tube 5/8" soft coil × 15 m | 1 | coil | Reece HVAC-R | $180 | $0 | Received | PO-26-0707 | |
| CU-H78-58 | Copper tube 7/8" hard drawn × 5.8 m | 2 | length | Reece HVAC-R | $245 | $0 | Received | PO-26-0707 | |
| CU-FIT-PK | Copper fittings pack — elbows, couplers, tees | 3 | pack | Reece HVAC-R | $167 | $0 | Received | PO-26-0707 | |
| INS-AF58 | Armaflex 5/8" ID × 19 mm × 1.8 m | 18 | length | Reece HVAC-R | $180 | $0 | Received | PO-26-0707 | |
| MS-SUND | Fixings & sundries allowance | 2 | lot | Reece HVAC-R | $70 | $0 | Received | PO-26-0707 | |
| EL-ISO20 | Isolator 20 A 2-pole IP66 | 1 | ea | Rexel Electrical | $36 | $0 | Received | PO-26-0711 | |
| EL-ISO35 | Isolator 35 A 3-pole IP66 | 1 | ea | Rexel Electrical | $58 | $0 | Received | PO-26-0711 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 20 | m | Rexel Electrical | $46 | $0 | Received | PO-26-0711 | |
| EL-5C4 | 4 mm² 5-core circular cable | 25 | m | Rexel Electrical | $148 | $0 | Received | PO-26-0711 | |
Purchase orders (6)All POs →
Invoices$32,429 of $32,429
INV-4246 Final10 Mar 2026 · MYOB #00004246
Paid$32,429 Timesheets — 112 hrs · $6,588 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 02 Mar 2026 | Sam Nguyen | 0 | $0 | — | |
| 02 Mar 2026 | Tayla Brooks | 0 | $0 | — | |
| 02 Mar 2026 | Craig Whitfield | 3 | $210 | — | |
| 02 Mar 2026 | Sam Nguyen | 7 | $532 | — | |
| 02 Mar 2026 | Tayla Brooks | 11 | $418 | — | |
| 02 Mar 2026 | Craig Whitfield | 8 | $560 | — | |
| 27 Feb 2026 | Sam Nguyen | 4 | $304 | — | |
| 27 Feb 2026 | Tayla Brooks | 11 | $418 | — | |
| 27 Feb 2026 | Craig Whitfield | 9 | $630 | — | |
| 26 Feb 2026 | Sam Nguyen | 7 | $532 | — | |
| 26 Feb 2026 | Tayla Brooks | 11 | $418 | — | |
| 26 Feb 2026 | Craig Whitfield | 11 | $770 | — | |
| 25 Feb 2026 | Sam Nguyen | 8 | $608 | Mobilise, set out | |
| 25 Feb 2026 | Tayla Brooks | 11 | $418 | Mobilise, set out | |
| 25 Feb 2026 | Craig Whitfield | 11 | $770 | Mobilise, set out | |