J-25-0102 · Kwinana — camp kitchen refrigeration

CSBP Kwinana · Kwinana — control room & labs · Refrigeration
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $58,618
27 Oct 2025 → 06 Nov 2025 · order PO 4796403 · from EST-25-0202 Rev A
Budget against actualOver budget
Job value
$58,618
ex GST
Budget cost
$41,630
margin 29%
Actual to date
$43,080
210.5 of 188 hrs
Forecast margin
$15,538
26.5% · $1,450 over budget
Materials
$30,870 / $30,870
Labour
$12,210 / $10,760
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
CSBP Kwinana
Site
Kwinana — control room & labs
Region
Kwinana
Access
Major hazard facility · permit to work
Site contact
Andrea Novak 08 9411 8777
Lead tech
Liam O'Brien
MYOB job
J-25-0102 in MYOB
Materials — from the estimate (18)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
RG-R448-10 Refrigerant R448A — 10 kg cylinder 3.2 cyl Actrol $1,829 $0 Received PO-25-0611
RG-N2-G Dry nitrogen — G size cylinder 2 cyl BOC Gas & Gear $196 $0 Received PO-25-0615
RG-BRZ15 Silver brazing rod 15% — 1 kg 1.3 pack BOC Gas & Gear $215 $0 Received PO-25-0615
HC-LET068 Heatcraft condensing unit 1.5 HP medium temp (R448A) 2 ea Heatcraft Australia $6,360 $0 Received PO-25-0613
HC-LET150 Heatcraft condensing unit 3.5 HP low temp (R448A) 2 ea Heatcraft Australia $11,920 $0 Received PO-25-0613
KB-EVMT26 Kirby coolroom evaporator, medium temp 2.6 kW 2 ea Kirby Refrigeration $2,480 $0 Received PO-25-0612
KB-EVLT30 Kirby freezer evaporator, low temp 3.0 kW electric defrost 2 ea Kirby Refrigeration $3,960 $0 Received PO-25-0612
CT-XR60 Dixell XR60CX coolroom controller kit 4 ea Kirby Refrigeration $1,240 $0 Received PO-25-0612
CU-C38-15 Copper tube 3/8" soft coil × 15 m 4 coil Reece HVAC-R $413 $0 Received PO-25-0610
CU-C58-15 Copper tube 5/8" soft coil × 15 m 2 coil Reece HVAC-R $360 $0 Received PO-25-0610
CU-H78-58 Copper tube 7/8" hard drawn × 5.8 m 4 length Reece HVAC-R $490 $0 Received PO-25-0610
CU-FIT-PK Copper fittings pack — elbows, couplers, tees 6 pack Reece HVAC-R $333 $0 Received PO-25-0610
INS-AF58 Armaflex 5/8" ID × 19 mm × 1.8 m 36 length Reece HVAC-R $360 $0 Received PO-25-0610
MS-SUND Fixings & sundries allowance 4 lot Reece HVAC-R $140 $0 Received PO-25-0610
EL-ISO20 Isolator 20 A 2-pole IP66 2 ea Rexel Electrical $72 $0 Received PO-25-0614
EL-ISO35 Isolator 35 A 3-pole IP66 2 ea Rexel Electrical $116 $0 Received PO-25-0614
EL-IC415 Interconnect cable 4C 1.5 mm² 40 m Rexel Electrical $92 $0 Received PO-25-0614
EL-5C4 4 mm² 5-core circular cable 50 m Rexel Electrical $295 $0 Received PO-25-0614
Timesheets — 210.5 hrs · $12,210 at cost
DateWhoHoursCostNote
04 Nov 2025 Sam Nguyen 0 $0 —
04 Nov 2025 Ben Harris 4.5 $144 —
04 Nov 2025 Liam O'Brien 9 $666 —
03 Nov 2025 Sam Nguyen 4 $304 —
03 Nov 2025 Ben Harris 11 $352 —
03 Nov 2025 Liam O'Brien 11 $814 —
03 Nov 2025 Sam Nguyen 8 $608 —
03 Nov 2025 Ben Harris 9 $288 —
03 Nov 2025 Liam O'Brien 9 $666 —
03 Nov 2025 Sam Nguyen 4 $304 —
03 Nov 2025 Ben Harris 11 $352 —
03 Nov 2025 Liam O'Brien 8 $592 —
31 Oct 2025 Sam Nguyen 7 $532 —
31 Oct 2025 Ben Harris 10 $320 —
31 Oct 2025 Liam O'Brien 9 $666 —
30 Oct 2025 Sam Nguyen 7 $532 —
30 Oct 2025 Ben Harris 11 $352 —
30 Oct 2025 Liam O'Brien 8 $592 —
29 Oct 2025 Sam Nguyen 6 $456 —
29 Oct 2025 Ben Harris 8 $256 —
29 Oct 2025 Liam O'Brien 8 $592 —
28 Oct 2025 Sam Nguyen 7 $532 —
28 Oct 2025 Ben Harris 8 $256 —
28 Oct 2025 Liam O'Brien 8 $592 —
27 Oct 2025 Sam Nguyen 6 $456 Mobilise, set out
27 Oct 2025 Ben Harris 10 $320 Mobilise, set out
27 Oct 2025 Liam O'Brien 9 $666 Mobilise, set out