WA HVAC

J-26-0128 · Units 1–14, Bibra Lake — rooftop unit replacement

Bibra Lake Business Park · Units 1–14, Bibra Lake · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $27,900
25 Jan 2026 → 01 Feb 2026 · order PO 4761592 · from EST-26-0221 Rev A
Budget against actualOn track
Job value
$27,900
ex GST
Budget cost
$21,753
margin 22%
Actual to date
$21,599
48.5 of 50 hrs
Forecast margin
$6,301
22.6% · $154 under budget
Materials
$18,705 / $18,705
Labour
$2,894 / $3,048
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Bibra Lake Business Park
Site
Units 1–14, Bibra Lake
Region
Bibra Lake
Access
Tenant notice 24 h
Site contact
Rachel Moreau 08 9418 6100
Lead tech
Ryan Teo
MYOB job
J-26-0128 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DU-GALV06 Galvanised sheet 0.6 mm 2400 × 1200 4 sheet BlueScope Distribution $184 $0 Received PO-26-0687
HR-EWP Scissor lift / EWP hire 2 day Coates $440 $0 Received PO-26-0688
DU-MASTIC Duct mastic & foil tape kit 2 kit Reece HVAC-R $44 $0 Received PO-26-0684
MS-SUND Fixings & sundries allowance 2 lot Reece HVAC-R $70 $0 Received PO-26-0684
EL-ISO35 Isolator 35 A 3-pole IP66 1 ea Rexel Electrical $58 $0 Received PO-26-0686
EL-5C4 4 mm² 5-core circular cable 10 m Rexel Electrical $59 $0 Received PO-26-0686
TZ-OPA303 Temperzone 30 kW packaged rooftop unit (OPA 303) 1 ea Temperzone $17,850 $0 Received PO-26-0685
Timesheets — 48.5 hrs · $2,894 at cost
DateWhoHoursCostNote
26 Jan 2026 Kyle Fraser 0 $0 —
26 Jan 2026 Sam Nguyen 2.5 $190 —
26 Jan 2026 Tayla Brooks 9 $342 —
26 Jan 2026 Ryan Teo 9 $648 —
26 Jan 2026 Kyle Fraser 4 $272 Mobilise, set out
26 Jan 2026 Sam Nguyen 5 $380 Mobilise, set out
26 Jan 2026 Tayla Brooks 9 $342 Mobilise, set out
26 Jan 2026 Ryan Teo 10 $720 Mobilise, set out