J-25-0119 · Mt Magnet gold project — rooftop unit replacement

Ramelius Resources · Mt Magnet gold project · Air Conditioning
MYOB · synced 09:14 Demo 08 Oct 2026
Invoiced · 100% complete
Invoiced $31,020
09 Jan 2026 → 14 Jan 2026 · order PO 4862163 · from EST-25-0214 Rev A
Budget against actualOn track
Job value
$31,020
ex GST
Budget cost
$23,853
margin 23%
Actual to date
$23,163
71 of 66 hrs
Forecast margin
$7,857
25.3% · $690 under budget
Materials
$18,705 / $18,705
Labour
$4,458 / $5,148
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
Client
Ramelius Resources
Site
Mt Magnet gold project
Region
Murchison · Mt Magnet
Access
FIFO 8/6 · site induction
Site contact
Hayden Price 08 9202 1127
Lead tech
Ryan Teo
MYOB job
J-25-0119 in MYOB
Materials — from the estimate (7)
CodeDescriptionQtyUnitSupplierBudgetAt today's priceStatusPO
DU-GALV06 Galvanised sheet 0.6 mm 2400 × 1200 4 sheet BlueScope Distribution $184 $0 Received PO-26-0679
HR-EWP Scissor lift / EWP hire 2 day Coates $440 $0 Received PO-26-0680
DU-MASTIC Duct mastic & foil tape kit 2 kit Reece HVAC-R $44 $0 Received PO-26-0676
MS-SUND Fixings & sundries allowance 2 lot Reece HVAC-R $70 $0 Received PO-26-0676
EL-ISO35 Isolator 35 A 3-pole IP66 1 ea Rexel Electrical $58 $0 Received PO-26-0678
EL-5C4 4 mm² 5-core circular cable 10 m Rexel Electrical $59 $0 Received PO-26-0678
TZ-OPA303 Temperzone 30 kW packaged rooftop unit (OPA 303) 1 ea Temperzone $17,850 $0 Received PO-26-0677
Timesheets — 71 hrs · $4,458 at cost
DateWhoHoursCostNote
12 Jan 2026 Ryan Teo 9 $648 —
12 Jan 2026 Kyle Fraser 7 $476 —
12 Jan 2026 Sam Nguyen 4 $304 —
12 Jan 2026 Tayla Brooks 10 $380 —
12 Jan 2026 Ryan Teo 11 $792 —
09 Jan 2026 Kyle Fraser 5 $340 Mobilise, set out
09 Jan 2026 Sam Nguyen 6 $456 Mobilise, set out
09 Jan 2026 Tayla Brooks 9 $342 Mobilise, set out
09 Jan 2026 Ryan Teo 10 $720 Mobilise, set out