Invoiced · 100% complete
Invoiced $23,378
02 Jan 2026 → 13 Jan 2026 · order PO 4753517 · from EST-25-0213 Rev A
Budget against actualOn track
Job value
$23,378
ex GST
Budget cost
$16,876
margin 28%
Actual to date
$15,318
69.5 of 72 hrs
Forecast margin
$8,060
34.5% · $1,558 under budget
Dark = spent (POs sent + timesheets at cost) · light = forecast to finish · line = budget from the estimate.
Site
- Client
- Ramelius Resources
- Site
- Mt Magnet gold project
- Region
- Murchison · Mt Magnet
- Access
- FIFO 8/6 · site induction
- Site contact
- Hayden Price 08 9202 1127
- Lead tech
- Craig Whitfield
- MYOB job
- J-25-0118 in MYOB
Materials — from the estimate (15)
| Code | Description | Qty | Unit | Supplier | Budget | At today's price | Status | PO | |
|---|---|---|---|---|---|---|---|---|---|
| CT-ZONE4 | 4-zone control system with touch screen | 1 | ea | Actrol | $860 | $0 | Received | PO-25-0666 | |
| RG-N2-G | Dry nitrogen — G size cylinder | 0.5 | cyl | BOC Gas & Gear | $49 | $0 | Received | PO-25-0670 | |
| DAI-FDYQ200 | Daikin 20.0 kW ducted split inverter, 3-ph (FDYQ200) | 1 | ea | Daikin Australia | $8,175 | $0 | Received | PO-25-0667 | |
| DU-FLX250 | Insulated flexible duct 250 mm × 6 m | 8 | length | Holyoake | $576 | $0 | Received | PO-25-0669 | |
| DU-DIF450 | Ceiling diffuser 4-way 450 sq. with plenum | 8 | ea | Holyoake | $368 | $0 | Received | PO-25-0669 | |
| DU-RAG600 | Return air grille 600 × 600 with filter | 2 | ea | Holyoake | $148 | $0 | Received | PO-25-0669 | |
| DU-SPG250 | Spigot collar 250 mm with damper | 8 | ea | Holyoake | $144 | $0 | Received | PO-25-0669 | |
| CU-PR3858 | Pre-insulated pair coil 3/8" + 5/8" × 20 m | 2 | coil | Reece HVAC-R | $655 | $0 | Received | PO-25-0665 | |
| DU-MASTIC | Duct mastic & foil tape kit | 3 | kit | Reece HVAC-R | $66 | $0 | Received | PO-25-0665 | |
| MS-STAND | Galvanised roof stand / plinth | 1 | ea | Reece HVAC-R | $145 | $0 | Received | PO-25-0665 | |
| MS-DRAIN | Condensate drain 20 mm PVC + fittings | 1 | set | Reece HVAC-R | $28 | $0 | Received | PO-25-0665 | |
| MS-SUND | Fixings & sundries allowance | 2 | lot | Reece HVAC-R | $70 | $0 | Received | PO-25-0665 | |
| EL-ISO35 | Isolator 35 A 3-pole IP66 | 1 | ea | Rexel Electrical | $58 | $0 | Received | PO-25-0668 | |
| EL-IC415 | Interconnect cable 4C 1.5 mm² | 30 | m | Rexel Electrical | $69 | $0 | Received | PO-25-0668 | |
| EL-5C4 | 4 mm² 5-core circular cable | 20 | m | Rexel Electrical | $118 | $0 | Received | PO-25-0668 | |
Purchase orders (6)All POs →
Invoices$23,378 of $23,378
INV-4225 Final14 Jan 2026 · MYOB #00004225
Paid$23,378 Timesheets — 69.5 hrs · $3,790 at cost
| Date | Who | Hours | Cost | Note | |
|---|---|---|---|---|---|
| 05 Jan 2026 | Ben Harris | 8.5 | $272 | — | |
| 05 Jan 2026 | Craig Whitfield | 8 | $560 | — | |
| 05 Jan 2026 | Sam Nguyen | 8 | $608 | — | |
| 05 Jan 2026 | Ben Harris | 11 | $352 | — | |
| 05 Jan 2026 | Craig Whitfield | 8 | $560 | — | |
| 02 Jan 2026 | Sam Nguyen | 6 | $456 | Mobilise, set out | |
| 02 Jan 2026 | Ben Harris | 11 | $352 | Mobilise, set out | |
| 02 Jan 2026 | Craig Whitfield | 9 | $630 | Mobilise, set out | |