WA HVAC

EST-26-0239 Rev A

Roy Hill Holdings · Roy Hill village — workshop exhaust & cooling
MYOB · synced 09:14 Demo 08 Oct 2026
Accepted
Accepted 12 Mar 2026 — job J-26-0155 raised
Roy Hill village · Pilbara · mine village · prepared by Matthew Jacka
Cost
$11,561
66 labour hrs · $5,128
Price ex GST
$16,721
22 lines · 3 groups
Margin
$5,160
30.9% of price
Total inc GST
$18,393
GST $1,672.06
Bill of materials & labour Accepted
ItemQtyUnitUnit costMarkupUnit sellLine
Exhaust fan & ducting — kitchen / ablutions × 2$5,337
FT-TD250
Fantech inline mixed-flow fan 250 mm (TD-1300/250)
2 ea $680.00 30% $884.00 $1,768.00
DU-FLX250
Insulated flexible duct 250 mm × 6 m
4 length $72.00 35% $97.20 $388.80
DU-SPG250
Spigot collar 250 mm with damper
4 ea $18.00 35% $24.30 $97.20
EL-ISO20
Isolator 20 A 2-pole IP66
2 ea $36.00 35% $48.60 $97.20
EL-TPS25
2.5 mm² TPS cable × 100 m
0.2 roll $160.00 30% $208.00 $41.60
MS-SUND
Fixings & sundries allowance
2 lot $35.00 35% $47.25 $94.50
LAB-MECH
Refrigeration mechanic
12 hr $72.00 73.6% $125.00 $1,500.00
LAB-ELEC
Electrician
6 hr $76.00 64.5% $125.00 $750.00
LAB-APP
Apprentice
8 hr $38.00 97.4% $75.00 $600.00
Wall split 7.1 kW — back-to-back install × 2$8,263
DAI-FTXM71
Daikin 7.1 kW wall split inverter (FTXM71)
2 ea $1,834.95 25% $2,293.69 $4,587.38
CU-PR1438
Pre-insulated pair coil 1/4" + 3/8" × 20 m
2 coil $238.00 35% $321.30 $642.60
MS-BRK750
Wall bracket 750 mm heavy duty, galv
2 pr $48.00 35% $64.80 $129.60
MS-PADS
Anti-vibration pads (set of 4)
2 set $22.00 35% $29.70 $59.40
EL-ISO20
Isolator 20 A 2-pole IP66
2 ea $36.00 35% $48.60 $97.20
EL-IC415
Interconnect cable 4C 1.5 mm²
24 m $2.29 40% $3.21 $77.04
MS-DRAIN
Condensate drain 20 mm PVC + fittings
2 set $28.00 35% $37.80 $75.60
MS-SUND
Fixings & sundries allowance
2 lot $35.00 35% $47.25 $94.50
LAB-MECH
Refrigeration mechanic
10 hr $72.00 73.6% $125.00 $1,250.00
LAB-APP
Apprentice
10 hr $38.00 97.4% $75.00 $750.00
LAB-ELEC
Electrician
4 hr $76.00 64.5% $125.00 $500.00
Regional mobilisation — 2-person crew$3,120
TRV-TIME
Travel time — regional (per person)
16 hr $60.00 50% $90.00 $1,440.00
TRV-KM
Service vehicle — regional travel
1,200 km $0.95 47.4% $1.40 $1,680.00
Scope & exclusions
Supply, install and commission as per the line items. Includes electrical isolation, refrigerant charge, testing and a commissioning report.
Exclusions: Builder's works, penetrations through fire-rated elements, after-hours work unless noted, structural certification. Flights and camp accommodation supplied by client on remote sites.
Client & site
Client
Roy Hill Holdings
Contact
Brendan Clancy · 08 6142 4000
Site
Roy Hill village
Access
FIFO · village access via camp admin
Terms
45 days EOM
Priced on
09 Mar 2026