EST-26-0270 Rev A

Bibra Lake Business Park · Units 1–14, Bibra Lake — switchroom cooling
MYOB · synced 09:14 Demo 08 Oct 2026
Declined
Declined 29 Jul 2026
Units 1–14, Bibra Lake · Bibra Lake · prepared by Matthew Jacka
Cost
$15,287
64 labour hrs · $3,992
Price ex GST
$21,380
13 lines · 1 groups
Margin
$6,093
28.5% of price
Total inc GST
$23,518
GST $2,138.04
Bill of materials & labour Declined
ItemQtyUnitUnit costMarkupUnit sellLine
Switchroom cooling — 2 × 7.1 kW duty/standby × 2$21,380
MEA-MSZAP71
Mitsubishi Electric 7.1 kW wall split (MSZ-AP71VG)
4 ea $2,040.00 25% $2,550.00 $10,200.00
CU-PR1438
Pre-insulated pair coil 1/4" + 3/8" × 20 m
4 coil $238.00 35% $321.30 $1,285.20
MS-BRK750
Wall bracket 750 mm heavy duty, galv
4 pr $48.00 35% $64.80 $259.20
MS-PADS
Anti-vibration pads (set of 4)
4 set $22.00 35% $29.70 $118.80
EL-ISO20
Isolator 20 A 2-pole IP66
4 ea $36.00 35% $48.60 $194.40
EL-IC415
Interconnect cable 4C 1.5 mm²
60 m $2.29 40% $3.21 $192.60
EL-CON25
Conduit 25 mm × 4 m + saddles
12 length $7.50 40% $10.50 $126.00
CT-DUTY
Duty / standby changeover controller with alarm relay
2 ea $640.00 30% $832.00 $1,664.00
MS-DRAIN
Condensate drain 20 mm PVC + fittings
4 set $28.00 35% $37.80 $151.20
MS-SUND
Fixings & sundries allowance
4 lot $35.00 35% $47.25 $189.00
LAB-MECH
Refrigeration mechanic
28 hr $72.00 73.6% $125.00 $3,500.00
LAB-APP
Apprentice
20 hr $38.00 97.4% $75.00 $1,500.00
LAB-ELEC
Electrician
16 hr $76.00 64.5% $125.00 $2,000.00
Scope & exclusions
Supply, install and commission as per the line items. Includes electrical isolation, refrigerant charge, testing and a commissioning report.
Exclusions: Builder's works, penetrations through fire-rated elements, after-hours work unless noted, structural certification. Flights and camp accommodation supplied by client on remote sites.
Client & site
Client
Bibra Lake Business Park
Contact
Rachel Moreau · 08 9418 6100
Site
Units 1–14, Bibra Lake
Access
Tenant notice 24 h
Terms
30 days EOM
Priced on