Declined
Declined 19 Jan 2026
St Ives gold mine — admin & crib rooms · Goldfields · Kambalda · prepared by Matthew Jacka
Cost
$15,955
72 labour hrs · $3,960
Price ex GST
$22,519
9 lines · 1 groups
Margin
$6,564
29.1% of price
Total inc GST
$24,771
GST $2,251.88
Bill of materials & labour Declined
| Item | Qty | Unit | Unit cost | Markup | Unit sell | Line | |
|---|---|---|---|---|---|---|---|
| Donga / transportable split 2.5 kW — per room × 12 | $22,519 | ||||||
| DAI-FTXF25 Daikin 2.5 kW wall split — transportable/donga (FTXF25) | 12 | ea | $737.86 | 25% | $922.33 | $11,067.96 | |
| CU-PR1438 Pre-insulated pair coil 1/4" + 3/8" × 20 m | 6 | coil | $227.75 | 35% | $307.46 | $1,844.76 | |
| MS-BRK750 Wall bracket 750 mm heavy duty, galv | 12 | pr | $48.00 | 35% | $64.80 | $777.60 | |
| EL-ISO20 Isolator 20 A 2-pole IP66 | 12 | ea | $36.00 | 35% | $48.60 | $583.20 | |
| EL-IC415 Interconnect cable 4C 1.5 mm² | 96 | m | $2.29 | 40% | $3.21 | $308.16 | |
| MS-DRAIN Condensate drain 20 mm PVC + fittings | 12 | set | $28.00 | 35% | $37.80 | $453.60 | |
| MS-SUND Fixings & sundries allowance | 6 | lot | $35.00 | 35% | $47.25 | $283.50 | |
| LAB-MECH Refrigeration mechanic | 36 | hr | $72.00 | 73.6% | $125.00 | $4,500.00 | |
| LAB-APP Apprentice | 36 | hr | $38.00 | 97.4% | $75.00 | $2,700.00 | |
Scope & exclusions
Supply, install and commission as per the line items. Includes electrical isolation, refrigerant charge, testing and a commissioning report.
Exclusions: Builder's works, penetrations through fire-rated elements, after-hours work unless noted, structural certification. Flights and camp accommodation supplied by client on remote sites.
Client & site
- Client
- Gold Fields Australia
- Contact
- Tom Ferreira · 08 9211 9200
- Site
- St Ives gold mine — admin & crib rooms
- Access
- DIDO · St Ives induction
- Terms
- 45 days EOM
- Priced on
- 29 Dec 2025