WA HVAC

Quotation EST-26-0241

CSBP Kwinana
MYOB · synced 09:14 Demo 08 Oct 2026
← Back to estimate
WA HVAC — Specialising in Mining & Resources
WA HVAC Pty Ltd
1/9 Blackly Row, Cockburn Central WA 6164 · 08 9314 7696 · admin@wahvac.com.au
ABN 49 629 340 405 · Refrigerant Trading Authorisation AU42942 · Electrical Contractor EC10155
Quotation
EST-26-0241 Rev A
Date 17 Mar 2026
Valid until 17 Apr 2026
Prepared by Matthew Jacka
Prepared for
CSBP Kwinana
Attn: Andrea Novak
andrea.novak@csbp.com.au
ABN 81 008 668 371
Site
Kwinana — control room & labs
Kwinana
Kwinana — donga AC changeover
DescriptionAmount ex GST
Donga / transportable split 2.5 kW — per room × 12
12 × Daikin 2.5 kW wall split — transportable/donga (FTXF25) · 6 × Pre-insulated pair coil 1/4" + 3/8" × 20 m · 12 × Wall bracket 750 mm heavy duty, galv · 12 × Isolator 20 A 2-pole IP66 · 96 × Interconnect cable 4C 1.5 mm² · 12 × Condensate drain 20 mm PVC + fittings · 6 × Fixings & sundries allowance · Installation, testing & commissioning (72 hrs)
$22,601.82
Subtotal (ex GST)$22,601.82
GST 10%$2,260.18
Total (inc GST)$24,862.00
This quotation is valid for 30 days. Prices are based on supplier costs on 16 Mar 2026. Exclusions: Builder's works, penetrations through fire-rated elements, after-hours work unless noted, structural certification. Flights and camp accommodation supplied by client on remote sites. Payment terms per our account terms. All work carried out by ARCtick-licensed technicians under RTA AU42942 and EC10155.